T-2025-0088 Demo Boyne Smelters Stockpile Shed: Re-clad & Acoustics
Accounting connected Thu 13 Aug 2026
T-2025-0088 Won Mining & Resources QJ2038

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Rio Tinto Aluminium · Boyne Island

Issued 14 Nov 2025 · closes 17 Jan 2026 · valid 90 days · Dylan Fraser

Price, ex GST

$2,542,100

Cost build-up

$2,165,756

Margin

$376,344 15%

Markup applied

26%

on the cost build-up

QClad

Roofing · Cladding · Acoustics

Estimate

T-2025-0088

Valid 90 days from 14 Nov 2025

To

Rio Tinto Aluminium

Grant Hollows, Superintendent, Fixed Plant

grant.hollows@riotinto.com

ABN 15 009 679 127

Job

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Boyne Island

Sector: Mining & Resources

Estimate closes 17 Jan 2026

Scope of works

Re-clad the stockpile shed and install an acoustic enclosure to the transfer tower, verified by independent sound test.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 1 item $18,450.00 $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 1 item $2,680.00 $2,680.00
RS-PRE-IND Site induction & verification of competency 14 ea $585.00 $8,190.00
RS-PRE-SUP Site supervision, leading hand 118 day $1,248.00 $147,264.00
RS-PRE-DEM Demobilisation & make good 1 item $7,420.00 $7,420.00
Wall cladding
RS-CLD-STR Strip existing wall cladding & dispose 4,260 m² $48.60 $207,036.00
RS-CLD-CUS CUSTOM ORB wall cladding, install 4,260 m² $107.80 $459,228.00
RS-CLD-FLA Custom flashings, supply and install 980 lm $114.00 $111,720.00
Roofing
RS-ROF-TRM TRIMDEK roof sheeting, install 1,880 m² $97.80 $183,864.00
Acoustics
RS-ACO-PNL Acoustic absorption panel, install 1,240 m² $229.00 $283,960.00
RS-ACO-LIN Perforated acoustic liner tray, install 860 m² $264.00 $227,040.00
RS-ACO-BAR Mass-loaded acoustic barrier mat, install 1,240 m² $156.00 $193,440.00
RS-ACO-ISO Isophonic bracket & resilient mount system 1,240 m² $89.40 $110,856.00
RS-ACO-ENC Plant acoustic enclosure, fabricate and install 380 m² $482.00 $183,160.00
RS-ACO-TST Post-installation acoustic verification test 1 item $4,280.00 $4,280.00
Height access
RS-HGT-ROP Rope access technician, IRATA 96 day $1,480.00 $142,080.00
RS-HGT-STA Static line system: supply, install & certify 320 lm $286.00 $91,520.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 2,640 lm $34.80 $91,872.00
RS-WPF-MEM Liquid-applied weatherproof membrane 420 m² $162.00 $68,040.00
Total, ex GST$2,542,100.00
GST at 10%$254,210.00
Total, inc GST$2,796,310.00

Exclusions

  • · Conveyor stoppage outside the nominated windows
  • · Structural steel

This tender is valid for 90 days from 14 Nov 2025 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320