Q27503 Demo Processing Building Townsville
Accounting connected Thu 13 Aug 2026
Q27503 Estimating - Submitted Mining & Resources

Processing Building Townsville

Budget shed pricing

Sedgman Pty Ltd · Townsville

Issued 12 Sep 2024 · closes 11 Oct 2024 · valid 30 days · Priya Raghavan

Two years old and still sitting on the board because nobody closes them out. This is exactly the housekeeping the migration cleans up.

Price, ex GST

$1,347,684

Cost build-up

$1,102,826

Margin

$244,858 18%

Markup applied

20%

on the cost build-up

QClad

Roofing · Cladding · Acoustics

Estimate

Q27503

Valid 30 days from 12 Sep 2024

To

Sedgman Pty Ltd

Anita Kolar, Lead Structural Engineer

anita.kolar@sedgman.com

ABN 20 088 471 667

Job

Processing Building Townsville

Townsville

Sector: Mining & Resources

Estimate closes 11 Oct 2024

Scope of works

Budget pricing only for the roof and wall cladding to a new processing building, for Sedgman's feasibility study. Rates current at the date of issue.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 2 item $18,450.00 $36,900.00
RS-PRE-SUP Site supervision, leading hand 118 day $1,248.00 $147,264.00
Roofing
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 3,200 m² $128.50 $411,200.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 3,200 m² $39.60 $126,720.00
RS-ROF-SAF Safety mesh, install to purlins 3,200 m² $24.80 $79,360.00
RS-ROF-GUT Box gutter, supply and install 240 lm $385.00 $92,400.00
Wall cladding
RS-CLD-CUS CUSTOM ORB wall cladding, install 2,400 m² $102.40 $245,760.00
RS-CLD-FLA Custom flashings, supply and install 1,180 lm $114.00 $134,520.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 24 ea $745.00 $17,880.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 1,600 lm $34.80 $55,680.00
Total, ex GST$1,347,684.00
GST at 10%$134,768.40
Total, inc GST$1,482,452.40

Exclusions

  • · This is a budget number for feasibility, not a firm price
  • · Structural steel
  • · Everything not expressly included

This tender is valid for 30 days from 12 Sep 2024 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320