C19512 Female Ablution Block
Groote Eylandt Mining Company · Groote Eylandt, NT
Issued 2 Aug 2026 · closes 30 Aug 2026 · valid 90 days · Priya Raghavan
Small package priced while the crew are already on the island for QJ2039, which is why the mobilisation line is nominal.
Price, ex GST
$202,150
Cost build-up
$166,617
Margin
$35,532 18%
Markup applied
26%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Estimate
Q32415
Valid 90 days from 2 Aug 2026
To
Groote Eylandt Mining Company
Warrick Delaney, Superintendent, Fixed Plant
w.delaney@gemco.com.au
ABN 51 009 265 006
Job
C19512 Female Ablution Block
Groote Eylandt, NT
Sector: Mining & Resources
Estimate closes 30 Aug 2026
Scope of works
Roof and wall cladding to a new female ablution block, including insulation, flashings, rainwater goods and weatherproofing.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 0.35 item | $18,450.00 | $6,457.50 |
| RS-PRE-IND Site induction & verification of competency | 4 ea | $585.00 | $2,340.00 |
| RS-PRE-SUP Site supervision, leading hand | 24 day | $1,248.00 | $29,952.00 |
| Roofing | |||
| RS-ROF-TRM TRIMDEK roof sheeting, install | 320 m² | $97.80 | $31,296.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 320 m² | $39.60 | $12,672.00 |
| RS-ROF-RDG Ridge capping & barge, supply and install | 64 lm | $146.00 | $9,344.00 |
| RS-ROF-GUT Box gutter, supply and install | 42 lm | $385.00 | $16,170.00 |
| RS-ROF-DWP Downpipe & rainhead, supply and install | 6 ea | $864.00 | $5,184.00 |
| Wall cladding | |||
| RS-CLD-CUS CUSTOM ORB wall cladding, install | 420 m² | $102.40 | $43,008.00 |
| RS-CLD-FLA Custom flashings, supply and install | 186 lm | $114.00 | $21,204.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 240 lm | $34.80 | $8,352.00 |
| Labour & plant | |||
| RS-LAB-TRV Travel & living away: per person, per day | 42 day | $385.00 | $16,170.00 |
| Total, ex GST | $202,149.50 |
| GST at 10% | $20,214.95 |
| Total, inc GST | $222,364.45 |
Exclusions
- · Barge freight
- · Plumbing, mechanical and electrical
- · Internal linings
This tender is valid for 90 days from 2 Aug 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320