Ravensworth Coal
Wall sheet and girt replacement
Glencore Coal Assets Australia · Ravensworth, NSW
Issued 18 Jul 2024 · closes 15 Aug 2024 · valid 90 days · Dylan Fraser
Glencore have re-issued this scope twice. The current lodgement is the third pass and the quantities have not moved since the second.
Price, ex GST
$1,366,084
Cost build-up
$1,132,349
Margin
$233,735 17%
Markup applied
26%
on the cost build-up
Roster and travel priced in
FIFO work is priced on the roster, not on a day rate. The trips are part of the number.
Swing
14 on, 7 off
Crew allocated
6
Trips required
5
Work hours per day
10
Roster days on
14
Cycles
3
QClad
Roofing · Cladding · Acoustics
Estimate
Q27693
Valid 90 days from 18 Jul 2024
To
Glencore Coal Assets Australia
Peter Rawson, Maintenance Superintendent
peter.rawson@glencore.com.au
ABN 31 121 522 664
Job
Ravensworth Coal
Ravensworth, NSW
Sector: Mining & Resources
Estimate closes 15 Aug 2024
Scope of works
Strip and replace corroded wall sheeting and girts to the CHPP and the reclaim tunnel headhouse, including flashings, cappings and weatherproofing.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 2 item | $18,450.00 | $36,900.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 2 item | $2,680.00 | $5,360.00 |
| RS-PRE-IND Site induction & verification of competency | 12 ea | $585.00 | $7,020.00 |
| RS-PRE-SUP Site supervision, leading hand | 96 day | $1,248.00 | $119,808.00 |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | 1,840 m² | $94.50 | $173,880.00 |
| RS-PRE-DEM Demobilisation & make good | 2 item | $7,420.00 | $14,840.00 |
| Wall cladding | |||
| RS-CLD-STR Strip existing wall cladding & dispose | 3,240 m² | $48.60 | $157,464.00 |
| RS-CLD-CUS CUSTOM ORB wall cladding, install | 3,240 m² | $102.40 | $331,776.00 |
| RS-CLD-FLA Custom flashings, supply and install | 1,420 lm | $114.00 | $161,880.00 |
| RS-CLD-CAP Corner & parapet capping, supply and install | 780 lm | $138.00 | $107,640.00 |
| Height access | |||
| RS-HGT-EWP EWP hire & operator, 45ft boom | 54 day | $1,780.00 | $96,120.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 1,620 lm | $34.80 | $56,376.00 |
| Labour & plant | |||
| RS-LAB-TRV Travel & living away: per person, per day | 252 day | $385.00 | $97,020.00 |
| Total, ex GST | $1,366,084.00 |
| GST at 10% | $136,608.40 |
| Total, inc GST | $1,502,692.40 |
Exclusions
- · Structural steel other than the girts nominated
- · Any work inside the reclaim tunnel
- · Asbestos identification or removal
This tender is valid for 90 days from 18 Jul 2024 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.