Hastings Deering
Remove and replace roofing, Wheel Ends roof
Hastings Deering (Australia) · Mackay
Issued 16 Jul 2026 · closes 22 Aug 2026 · valid 60 days · Priya Raghavan
Hastings Deering have accepted the price and are on QClad's subcontract terms rather than their own, which is why it is sitting in review rather than won.
Price, ex GST
$1,084,248
Cost build-up
$898,667
Margin
$185,581 17%
Markup applied
24%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Estimate
Q32441
Valid 60 days from 16 Jul 2026
To
Hastings Deering (Australia)
Trent Vasilakis, Facilities Coordinator
trent.vasilakis@hastingsdeering.com.au
ABN 26 054 094 647
Job
Hastings Deering
Mackay
Sector: Industrial
Estimate closes 22 Aug 2026
Scope of works
Strip and replace the Wheel Ends workshop roof in KLIP-LOK 700, renew safety mesh and roof lighting, replace box gutters and downpipes, and install a permanent anchor and static line system.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 1 item | $18,450.00 | $18,450.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 1 item | $2,680.00 | $2,680.00 |
| RS-PRE-IND Site induction & verification of competency | 10 ea | $585.00 | $5,850.00 |
| RS-PRE-SUP Site supervision, leading hand | 78 day | $1,248.00 | $97,344.00 |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | 860 m² | $94.50 | $81,270.00 |
| RS-PRE-DEM Demobilisation & make good | 1 item | $7,420.00 | $7,420.00 |
| Roofing | |||
| RS-ROF-STR Strip existing roof sheeting & dispose | 2,180 m² | $52.40 | $114,232.00 |
| RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install | 2,180 m² | $128.50 | $280,130.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 2,180 m² | $39.60 | $86,328.00 |
| RS-ROF-SAF Safety mesh, install to purlins | 2,180 m² | $24.80 | $54,064.00 |
| RS-ROF-SKY Fibreglass roof lighting, install | 186 m² | $198.00 | $36,828.00 |
| RS-ROF-GUT Box gutter, supply and install | 218 lm | $385.00 | $83,930.00 |
| RS-ROF-DWP Downpipe & rainhead, supply and install | 22 ea | $864.00 | $19,008.00 |
| Height access | |||
| RS-HGT-ANC Roof anchor point: supply, install & certify | 26 ea | $745.00 | $19,370.00 |
| RS-HGT-STA Static line system: supply, install & certify | 240 lm | $286.00 | $68,640.00 |
| RS-HGT-EWP EWP hire & operator, 45ft boom | 38 day | $1,780.00 | $67,640.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 1,180 lm | $34.80 | $41,064.00 |
| Total, ex GST | $1,084,248.00 |
| GST at 10% | $108,424.80 |
| Total, inc GST | $1,192,672.80 |
Exclusions
- · Any work requiring the workshop to close
- · Relocation of overhead cranes or services
- · Asbestos identification or removal
This tender is valid for 60 days from 16 Jul 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320