Mineral Sands Plant
Ausenco, Capel MSP project
Ausenco Services · Capel, WA
Issued 18 Nov 2025 · closes 18 Dec 2025 · valid 120 days · Dylan Fraser
First time pricing for Ausenco in WA. Freight and the roster carry the risk rather than the trade.
Price, ex GST
$2,570,588
Cost build-up
$2,104,218
Margin
$466,370 18%
Markup applied
25%
on the cost build-up
Roster and travel priced in
FIFO work is priced on the roster, not on a day rate. The trips are part of the number.
Swing
14 on, 7 off
Crew allocated
8
Trips required
7
Work hours per day
10
Roster days on
14
Cycles
4
QClad
Roofing · Cladding · Acoustics
Estimate
Q22087
Valid 120 days from 18 Nov 2025
To
Ausenco Services
Marcus Ellery, Package Engineer
marcus.ellery@ausenco.com
ABN 76 010 761 943
Job
Mineral Sands Plant
Capel, WA
Sector: Mining & Resources
Estimate closes 18 Dec 2025
Scope of works
Cladding and acoustic treatment to the mineral sands plant: insulated panel to the process building, mass-loaded barrier and absorption panel to the screening tower, roof sheeting throughout and a verification test at the boundary.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 3 item | $18,450.00 | $55,350.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 3 item | $2,680.00 | $8,040.00 |
| RS-PRE-IND Site induction & verification of competency | 16 ea | $585.00 | $9,360.00 |
| RS-PRE-SUP Site supervision, leading hand | 168 day | $1,248.00 | $209,664.00 |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | 1,620 m² | $94.50 | $153,090.00 |
| RS-PRE-DEM Demobilisation & make good | 3 item | $7,420.00 | $22,260.00 |
| Roofing | |||
| RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install | 2,840 m² | $128.50 | $364,940.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 2,840 m² | $39.60 | $112,464.00 |
| RS-ROF-SAF Safety mesh, install to purlins | 2,840 m² | $24.80 | $70,432.00 |
| Wall cladding | |||
| RS-CLD-KSP Kingspan KS1000 RW insulated panel, install | 2,180 m² | $278.00 | $606,040.00 |
| RS-CLD-FLA Custom flashings, supply and install | 1,080 lm | $114.00 | $123,120.00 |
| Acoustics | |||
| RS-ACO-BAR Mass-loaded acoustic barrier mat, install | 1,240 m² | $156.00 | $193,440.00 |
| RS-ACO-PNL Acoustic absorption panel, install | 860 m² | $229.00 | $196,940.00 |
| RS-ACO-ISO Isophonic bracket & resilient mount system | 1,240 m² | $89.40 | $110,856.00 |
| RS-ACO-TST Post-installation acoustic verification test | 1 item | $4,280.00 | $4,280.00 |
| Height access | |||
| RS-HGT-ANC Roof anchor point: supply, install & certify | 32 ea | $745.00 | $23,840.00 |
| RS-HGT-STA Static line system: supply, install & certify | 320 lm | $286.00 | $91,520.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 1,840 lm | $34.80 | $64,032.00 |
| Labour & plant | |||
| RS-LAB-TRV Travel & living away: per person, per day | 392 day | $385.00 | $150,920.00 |
| Total, ex GST | $2,570,588.00 |
| GST at 10% | $257,058.80 |
| Total, inc GST | $2,827,646.80 |
Exclusions
- · Structural steel
- · Mechanical and electrical
- · Interstate freight above the allowance shown
- · Any acoustic performance guarantee beyond the specified 42 dB(A)
This tender is valid for 120 days from 18 Nov 2025 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320