QClad
QClad
Q22087 Demo Mineral Sands Plant
Accounting connected Thu 13 Aug 2026
Q22087 Estimating - Submitted Mining & Resources 14/7 · 8 crew · 7 trips

Mineral Sands Plant

Ausenco, Capel MSP project

Ausenco Services · Capel, WA

Issued 18 Nov 2025 · closes 18 Dec 2025 · valid 120 days · Dylan Fraser

First time pricing for Ausenco in WA. Freight and the roster carry the risk rather than the trade.

Price, ex GST

$2,570,588

Cost build-up

$2,104,218

Margin

$466,370 18%

Markup applied

25%

on the cost build-up

Roster and travel priced in

FIFO work is priced on the roster, not on a day rate. The trips are part of the number.

Swing

14 on, 7 off

Crew allocated

8

Trips required

7

Work hours per day

10

Roster days on

14

Cycles

4

QClad

Roofing · Cladding · Acoustics

Estimate

Q22087

Valid 120 days from 18 Nov 2025

To

Ausenco Services

Marcus Ellery, Package Engineer

marcus.ellery@ausenco.com

ABN 76 010 761 943

Job

Mineral Sands Plant

Capel, WA

Sector: Mining & Resources

Estimate closes 18 Dec 2025

Scope of works

Cladding and acoustic treatment to the mineral sands plant: insulated panel to the process building, mass-loaded barrier and absorption panel to the screening tower, roof sheeting throughout and a verification test at the boundary.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 3 item $18,450.00 $55,350.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 3 item $2,680.00 $8,040.00
RS-PRE-IND Site induction & verification of competency 16 ea $585.00 $9,360.00
RS-PRE-SUP Site supervision, leading hand 168 day $1,248.00 $209,664.00
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle 1,620 m² $94.50 $153,090.00
RS-PRE-DEM Demobilisation & make good 3 item $7,420.00 $22,260.00
Roofing
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 2,840 m² $128.50 $364,940.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 2,840 m² $39.60 $112,464.00
RS-ROF-SAF Safety mesh, install to purlins 2,840 m² $24.80 $70,432.00
Wall cladding
RS-CLD-KSP Kingspan KS1000 RW insulated panel, install 2,180 m² $278.00 $606,040.00
RS-CLD-FLA Custom flashings, supply and install 1,080 lm $114.00 $123,120.00
Acoustics
RS-ACO-BAR Mass-loaded acoustic barrier mat, install 1,240 m² $156.00 $193,440.00
RS-ACO-PNL Acoustic absorption panel, install 860 m² $229.00 $196,940.00
RS-ACO-ISO Isophonic bracket & resilient mount system 1,240 m² $89.40 $110,856.00
RS-ACO-TST Post-installation acoustic verification test 1 item $4,280.00 $4,280.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 32 ea $745.00 $23,840.00
RS-HGT-STA Static line system: supply, install & certify 320 lm $286.00 $91,520.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 1,840 lm $34.80 $64,032.00
Labour & plant
RS-LAB-TRV Travel & living away: per person, per day 392 day $385.00 $150,920.00
Total, ex GST$2,570,588.00
GST at 10%$257,058.80
Total, inc GST$2,827,646.80

Exclusions

  • · Structural steel
  • · Mechanical and electrical
  • · Interstate freight above the allowance shown
  • · Any acoustic performance guarantee beyond the specified 42 dB(A)

This tender is valid for 120 days from 18 Nov 2025 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320