QClad
QClad
Q32235 Demo The Mine, Burnett Highway
Accounting connected Thu 13 Aug 2026
Q32235 Contract Review Mining & Resources 14/7 · 8 crew · 6 trips

The Mine, Burnett Highway

H1 Morgan extra buildings

Morgan Projects · Burnett Highway

Issued 28 Feb 2026 · closes 29 Mar 2026 · valid 120 days · Dylan Fraser

Awarded subject to contract. Legal are on the liquidated damages clause, which as drafted is uncapped. Nothing starts until that is resolved.

Price, ex GST

$3,051,040

Cost build-up

$2,476,170

Margin

$574,871 19%

Markup applied

26%

on the cost build-up

Roster and travel priced in

FIFO work is priced on the roster, not on a day rate. The trips are part of the number.

Swing

14 on, 7 off

Crew allocated

8

Trips required

6

Work hours per day

10

Roster days on

14

Cycles

3

QClad

Roofing · Cladding · Acoustics

Estimate

Q32235

Valid 120 days from 28 Feb 2026

To

Morgan Projects

Bill Rennick, Construction Manager

brennick@morganprojects.com.au

ABN 63 122 048 812

Job

The Mine, Burnett Highway

Burnett Highway

Sector: Mining & Resources

Estimate closes 29 Mar 2026

Scope of works

Roof and wall cladding to the H1 extra buildings: workshop, wash bay, store and crib. Insulated panel to the crib, sheet elsewhere, with permanent access systems throughout.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 3 item $18,450.00 $55,350.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 3 item $2,680.00 $8,040.00
RS-PRE-IND Site induction & verification of competency 18 ea $585.00 $10,530.00
RS-PRE-SUP Site supervision, leading hand 186 day $1,248.00 $232,128.00
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle 1,480 m² $94.50 $139,860.00
RS-PRE-DEM Demobilisation & make good 3 item $7,420.00 $22,260.00
Roofing
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 4,620 m² $128.50 $593,670.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 4,620 m² $39.60 $182,952.00
RS-ROF-SAF Safety mesh, install to purlins 4,620 m² $24.80 $114,576.00
RS-ROF-RDG Ridge capping & barge, supply and install 520 lm $146.00 $75,920.00
RS-ROF-GUT Box gutter, supply and install 340 lm $385.00 $130,900.00
RS-ROF-DWP Downpipe & rainhead, supply and install 38 ea $864.00 $32,832.00
Wall cladding
RS-CLD-CUS CUSTOM ORB wall cladding, install 3,180 m² $102.40 $325,632.00
RS-CLD-KSP Kingspan KS1000 RW insulated panel, install 940 m² $278.00 $261,320.00
RS-CLD-FLA Custom flashings, supply and install 1,460 lm $114.00 $166,440.00
RS-CLD-CAP Corner & parapet capping, supply and install 820 lm $138.00 $113,160.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 46 ea $745.00 $34,270.00
RS-HGT-STA Static line system: supply, install & certify 420 lm $286.00 $120,120.00
RS-HGT-EWP EWP hire & operator, 45ft boom 78 day $1,780.00 $138,840.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 2,380 lm $34.80 $82,824.00
RS-WPF-PEN Roof penetration flashing, form & seal 54 ea $684.00 $36,936.00
Labour & plant
RS-LAB-TRV Travel & living away: per person, per day 448 day $385.00 $172,480.00
Total, ex GST$3,051,040.00
GST at 10%$305,104.00
Total, inc GST$3,356,144.00

Exclusions

  • · Structural steel and purlins
  • · Concrete and civil
  • · Liquidated damages beyond 5% of the subcontract sum

This tender is valid for 120 days from 28 Feb 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms BIF 15/25, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320