The Mine, Burnett Highway
H1 Morgan extra buildings
Morgan Projects · Burnett Highway
Issued 28 Feb 2026 · closes 29 Mar 2026 · valid 120 days · Dylan Fraser
Awarded subject to contract. Legal are on the liquidated damages clause, which as drafted is uncapped. Nothing starts until that is resolved.
Price, ex GST
$3,051,040
Cost build-up
$2,476,170
Margin
$574,871 19%
Markup applied
26%
on the cost build-up
Roster and travel priced in
FIFO work is priced on the roster, not on a day rate. The trips are part of the number.
Swing
14 on, 7 off
Crew allocated
8
Trips required
6
Work hours per day
10
Roster days on
14
Cycles
3
QClad
Roofing · Cladding · Acoustics
Estimate
Q32235
Valid 120 days from 28 Feb 2026
To
Morgan Projects
Bill Rennick, Construction Manager
brennick@morganprojects.com.au
ABN 63 122 048 812
Job
The Mine, Burnett Highway
Burnett Highway
Sector: Mining & Resources
Estimate closes 29 Mar 2026
Scope of works
Roof and wall cladding to the H1 extra buildings: workshop, wash bay, store and crib. Insulated panel to the crib, sheet elsewhere, with permanent access systems throughout.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 3 item | $18,450.00 | $55,350.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 3 item | $2,680.00 | $8,040.00 |
| RS-PRE-IND Site induction & verification of competency | 18 ea | $585.00 | $10,530.00 |
| RS-PRE-SUP Site supervision, leading hand | 186 day | $1,248.00 | $232,128.00 |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | 1,480 m² | $94.50 | $139,860.00 |
| RS-PRE-DEM Demobilisation & make good | 3 item | $7,420.00 | $22,260.00 |
| Roofing | |||
| RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install | 4,620 m² | $128.50 | $593,670.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 4,620 m² | $39.60 | $182,952.00 |
| RS-ROF-SAF Safety mesh, install to purlins | 4,620 m² | $24.80 | $114,576.00 |
| RS-ROF-RDG Ridge capping & barge, supply and install | 520 lm | $146.00 | $75,920.00 |
| RS-ROF-GUT Box gutter, supply and install | 340 lm | $385.00 | $130,900.00 |
| RS-ROF-DWP Downpipe & rainhead, supply and install | 38 ea | $864.00 | $32,832.00 |
| Wall cladding | |||
| RS-CLD-CUS CUSTOM ORB wall cladding, install | 3,180 m² | $102.40 | $325,632.00 |
| RS-CLD-KSP Kingspan KS1000 RW insulated panel, install | 940 m² | $278.00 | $261,320.00 |
| RS-CLD-FLA Custom flashings, supply and install | 1,460 lm | $114.00 | $166,440.00 |
| RS-CLD-CAP Corner & parapet capping, supply and install | 820 lm | $138.00 | $113,160.00 |
| Height access | |||
| RS-HGT-ANC Roof anchor point: supply, install & certify | 46 ea | $745.00 | $34,270.00 |
| RS-HGT-STA Static line system: supply, install & certify | 420 lm | $286.00 | $120,120.00 |
| RS-HGT-EWP EWP hire & operator, 45ft boom | 78 day | $1,780.00 | $138,840.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 2,380 lm | $34.80 | $82,824.00 |
| RS-WPF-PEN Roof penetration flashing, form & seal | 54 ea | $684.00 | $36,936.00 |
| Labour & plant | |||
| RS-LAB-TRV Travel & living away: per person, per day | 448 day | $385.00 | $172,480.00 |
| Total, ex GST | $3,051,040.00 |
| GST at 10% | $305,104.00 |
| Total, inc GST | $3,356,144.00 |
Exclusions
- · Structural steel and purlins
- · Concrete and civil
- · Liquidated damages beyond 5% of the subcontract sum
This tender is valid for 120 days from 28 Feb 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms BIF 15/25, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320