Q32916 Demo Hillgrove Mine
Accounting connected Thu 13 Aug 2026
Q32916 Estimating - Pending Mining & Resources 14/7 · 8 crew · 6 trips

Hillgrove Mine

Concentrate Filter Extension, Tails Filter Building

MACA Interquip · Hillgrove Mine, Armidale NSW

Issued 27 Jan 2026 · closes 2 Mar 2026 · valid 90 days · Dylan Fraser

MACA extended the close twice. Priced on a 14 and 7 out of Armidale with six trips for a crew of eight.

Price, ex GST

$2,698,446

Cost build-up

$2,180,578

Margin

$517,868 19%

Markup applied

26%

on the cost build-up

Roster and travel priced in

FIFO work is priced on the roster, not on a day rate. The trips are part of the number.

Swing

14 on, 7 off

Crew allocated

8

Trips required

6

Work hours per day

10

Roster days on

14

Cycles

3

QClad

Roofing · Cladding · Acoustics

Estimate

Q32916

Valid 90 days from 27 Jan 2026

To

MACA Interquip

Grant Tolhurst, Project Manager

g.tolhurst@maca.com.au

ABN 42 144 745 782

Job

Hillgrove Mine

Hillgrove Mine, Armidale NSW

Sector: Mining & Resources

Estimate closes 2 Mar 2026

Scope of works

Roof and wall cladding to the concentrate filter extension and the tails filter building, including insulated panel to the filter room, safety mesh, anchor and static line systems and full weatherproofing.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 2 item $18,450.00 $36,900.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 2 item $2,680.00 $5,360.00
RS-PRE-IND Site induction & verification of competency 16 ea $585.00 $9,360.00
RS-PRE-SUP Site supervision, leading hand 148 day $1,248.00 $184,704.00
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle 1,240 m² $94.50 $117,180.00
RS-PRE-DEM Demobilisation & make good 2 item $7,420.00 $14,840.00
Roofing
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 3,180 m² $128.50 $408,630.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 3,180 m² $39.60 $125,928.00
RS-ROF-SAF Safety mesh, install to purlins 3,180 m² $24.80 $78,864.00
RS-ROF-RDG Ridge capping & barge, supply and install 386 lm $146.00 $56,356.00
RS-ROF-GUT Box gutter, supply and install 218 lm $385.00 $83,930.00
Wall cladding
RS-CLD-KSP Kingspan KS1000 RW insulated panel, install 2,460 m² $278.00 $683,880.00
RS-CLD-CUS CUSTOM ORB wall cladding, install 1,840 m² $102.40 $188,416.00
RS-CLD-FLA Custom flashings, supply and install 1,120 lm $114.00 $127,680.00
RS-CLD-CAP Corner & parapet capping, supply and install 640 lm $138.00 $88,320.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 34 ea $745.00 $25,330.00
RS-HGT-STA Static line system: supply, install & certify 288 lm $286.00 $82,368.00
RS-HGT-EWP EWP hire & operator, 45ft boom 62 day $1,780.00 $110,360.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 1,860 lm $34.80 $64,728.00
RS-WPF-PEN Roof penetration flashing, form & seal 48 ea $684.00 $32,832.00
Labour & plant
RS-LAB-TRV Travel & living away: per person, per day 448 day $385.00 $172,480.00
Total, ex GST$2,698,446.00
GST at 10%$269,844.60
Total, inc GST$2,968,290.60

Exclusions

  • · Structural steel and purlins
  • · Louvres and mechanical penetrations by others
  • · Site accommodation beyond the camp allowance
  • · Crane hire beyond the allowance shown

This tender is valid for 90 days from 27 Jan 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms BIF 15/25, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320