Q32400 Demo Mooloolah Valley Distribution Reservoir
Accounting connected Thu 13 Aug 2026
Q32400 Estimating - Pending Industrial

Mooloolah Valley Distribution Reservoir

Mooloolah Valley Distribution Reservoir Renewal

Dornway Civil · Mooloolah Valley

Issued 20 Jul 2026 · closes 14 Aug 2026 · valid 60 days · Dylan Fraser

Dornway asked for a reduced-scope option on 30 Jul 2026 and both are priced. Option A is current until they say otherwise.

Price, ex GST

$724,376

Cost build-up

$602,300

Margin

$122,076 17%

Markup applied

22%

on the cost build-up

Options

Priced alternatives raised while the scope was still moving. The current one is what the price above reflects, so when the client comes back in three weeks asking what happened to option B, the answer is on the record.

OptionScopePrice, ex GSTAgainst currentState
A Full roof renewal, KLIP-LOK 700 $724,376 - Current
B Sheet replacement to damaged bays only Client asked for a reduced scope on 30 Jul 2026. $311,482 -$412,894 Superseded

QClad

Roofing · Cladding · Acoustics

Estimate

Q32400

Valid 60 days from 20 Jul 2026

To

Dornway Civil

Peter Nagy, Contracts Administrator

pnagy@dornway.com.au

ABN 64 129 774 218

Job

Mooloolah Valley Distribution Reservoir

Mooloolah Valley

Sector: Industrial

Estimate closes 14 Aug 2026

Scope of works

Strip and renew the reservoir roof in KLIP-LOK 700, replace corroded purlins on a provisional quantity, renew safety mesh, ridge and rainwater goods, and install an anchor and static line system for future access.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 1 item $18,450.00 $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 1 item $2,680.00 $2,680.00
RS-PRE-IND Site induction & verification of competency 8 ea $585.00 $4,680.00
RS-PRE-SUP Site supervision, leading hand 62 day $1,248.00 $77,376.00
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle 620 m² $94.50 $58,590.00
RS-PRE-DEM Demobilisation & make good 1 item $7,420.00 $7,420.00
Roofing
RS-ROF-STR Strip existing roof sheeting & dispose 1,840 m² $52.40 $96,416.00
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 1,840 m² $128.50 $236,440.00
RS-ROF-SAF Safety mesh, install to purlins 1,840 m² $24.80 $45,632.00
RS-ROF-RDG Ridge capping & barge, supply and install 186 lm $146.00 $27,156.00
RS-ROF-GUT Box gutter, supply and install 124 lm $385.00 $47,740.00
RS-ROF-DWP Downpipe & rainhead, supply and install 14 ea $864.00 $12,096.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 12 ea $745.00 $8,940.00
RS-HGT-STA Static line system: supply, install & certify 168 lm $286.00 $48,048.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 940 lm $34.80 $32,712.00
Total, ex GST$724,376.00
GST at 10%$72,437.60
Total, inc GST$796,813.60

Exclusions

  • · Potable water disinfection and re-commissioning
  • · Asbestos identification or removal
  • · Structural steel beyond the provisional purlin quantity
  • · Night work

This tender is valid for 60 days from 20 Jul 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320