Q27686 Demo Bengalla CHPP
Accounting connected Thu 13 Aug 2026
Q27686 Estimating - Submitted Mining & Resources 14/7 · 10 crew · 8 trips

Bengalla CHPP

Coal Preparation Plant reroof

Family Constructions · Bengalla Mine, Muswellbrook

Issued 5 Jun 2026 · closes 5 Jul 2026 · valid 120 days · Dylan Fraser

Live plant beneath, permit to work every shift, and the conveyor cannot stop outside the nominated windows. That is the whole risk and it is priced into the supervision and the shutdown allowance.

Price, ex GST

$2,796,934

Cost build-up

$2,277,852

Margin

$519,082 19%

Markup applied

28%

on the cost build-up

Roster and travel priced in

FIFO work is priced on the roster, not on a day rate. The trips are part of the number.

Swing

14 on, 7 off

Crew allocated

10

Trips required

8

Work hours per day

10

Roster days on

14

Cycles

3

QClad

Roofing · Cladding · Acoustics

Estimate

Q27686

Valid 120 days from 5 Jun 2026

To

Family Constructions

Joe Falzon, Contracts Manager

joe@familyconstructions.com.au

ABN 89 003 561 187

Job

Bengalla CHPP

Bengalla Mine, Muswellbrook

Sector: Mining & Resources

Estimate closes 5 Jul 2026

Scope of works

Full re-roof of the coal preparation plant over live process equipment: strip, purlin renewal on a provisional quantity, KLIP-LOK 700, insulation, safety mesh, ridge ventilators and a permanent static line system.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 3 item $18,450.00 $55,350.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 3 item $2,680.00 $8,040.00
RS-PRE-IND Site induction & verification of competency 20 ea $585.00 $11,700.00
RS-PRE-SUP Site supervision, leading hand 218 day $1,248.00 $272,064.00
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle 2,460 m² $94.50 $232,470.00
RS-PRE-DEM Demobilisation & make good 3 item $7,420.00 $22,260.00
Roofing
RS-ROF-STR Strip existing roof sheeting & dispose 4,180 m² $52.40 $219,032.00
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 4,180 m² $139.40 $582,692.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 4,180 m² $39.60 $165,528.00
RS-ROF-SAF Safety mesh, install to purlins 4,180 m² $24.80 $103,664.00
RS-ROF-VNT Ridge ventilator, supply and install 186 lm $624.00 $116,064.00
RS-ROF-RDG Ridge capping & barge, supply and install 420 lm $146.00 $61,320.00
RS-ROF-GUT Box gutter, supply and install 268 lm $385.00 $103,180.00
RS-ROF-DWP Downpipe & rainhead, supply and install 28 ea $864.00 $24,192.00
Wall cladding
RS-CLD-STR Strip existing wall cladding & dispose 1,640 m² $48.60 $79,704.00
RS-CLD-CUS CUSTOM ORB wall cladding, install 1,640 m² $102.40 $167,936.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 42 ea $745.00 $31,290.00
RS-HGT-STA Static line system: supply, install & certify 480 lm $286.00 $137,280.00
RS-HGT-SPI Spider lift hire & operator, 28m 34 day $2,360.00 $80,240.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 2,180 lm $34.80 $75,864.00
RS-WPF-PEN Roof penetration flashing, form & seal 46 ea $684.00 $31,464.00
Labour & plant
RS-LAB-TRV Travel & living away: per person, per day 560 day $385.00 $215,600.00
Total, ex GST$2,796,934.00
GST at 10%$279,693.40
Total, inc GST$3,076,627.40

Exclusions

  • · Any work requiring the plant to stop outside the nominated shutdown
  • · Dust suppression
  • · Asbestos identification or removal
  • · Structural design

This tender is valid for 120 days from 5 Jun 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms BIF 15/25, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320