Logan Hyperdome
Roof renewal to the northern retail wing
ADCO Constructions · Loganholme
Issued 8 Jul 2026 · closes 3 Aug 2026 · valid 60 days · Priya Raghavan
Trading centre. Everything happens between 10pm and 5am and the price carries a night allowance in the supervision line.
Price, ex GST
$1,852,362
Cost build-up
$1,515,261
Margin
$337,101 18%
Markup applied
21%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Estimate
Q32592
Valid 60 days from 8 Jul 2026
To
ADCO Constructions
Nadia Petkovic, Contracts Administrator
npetkovic@adcoconstruct.com.au
ABN 44 000 025 651
Job
Logan Hyperdome
Loganholme
Sector: Commercial
Estimate closes 3 Aug 2026
Scope of works
Strip and re-sheet the northern retail wing in KLIP-LOK 406, renew box gutters and rainwater goods, install a permanent anchor and static line system, and weatherproof all penetrations. Trading centre, so all work is out of hours.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 2 item | $18,450.00 | $36,900.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 2 item | $2,680.00 | $5,360.00 |
| RS-PRE-IND Site induction & verification of competency | 14 ea | $585.00 | $8,190.00 |
| RS-PRE-SUP Site supervision, leading hand | 118 day | $1,480.00 | $174,640.00 |
| RS-PRE-DEM Demobilisation & make good | 2 item | $7,420.00 | $14,840.00 |
| Roofing | |||
| RS-ROF-STR Strip existing roof sheeting & dispose | 4,260 m² | $52.40 | $223,224.00 |
| RS-ROF-KL4 KLIP-LOK 406 roof sheeting, install | 4,260 m² | $116.40 | $495,864.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 4,260 m² | $39.60 | $168,696.00 |
| RS-ROF-SAF Safety mesh, install to purlins | 4,260 m² | $24.80 | $105,648.00 |
| RS-ROF-GUT Box gutter, supply and install | 386 lm | $385.00 | $148,610.00 |
| RS-ROF-DWP Downpipe & rainhead, supply and install | 42 ea | $864.00 | $36,288.00 |
| RS-ROF-SKY Fibreglass roof lighting, install | 240 m² | $198.00 | $47,520.00 |
| Height access | |||
| RS-HGT-ANC Roof anchor point: supply, install & certify | 46 ea | $745.00 | $34,270.00 |
| RS-HGT-STA Static line system: supply, install & certify | 420 lm | $286.00 | $120,120.00 |
| RS-HGT-EWP EWP hire & operator, 45ft boom | 64 day | $1,780.00 | $113,920.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 2,180 lm | $34.80 | $75,864.00 |
| RS-WPF-PEN Roof penetration flashing, form & seal | 62 ea | $684.00 | $42,408.00 |
| Total, ex GST | $1,852,362.00 |
| GST at 10% | $185,236.20 |
| Total, inc GST | $2,037,598.20 |
Exclusions
- · Mechanical plant relocation
- · Internal ceiling protection
- · Traffic management to the car park
- · Trade waste beyond the bins allowed
This tender is valid for 60 days from 8 Jul 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms BIF 15/25, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320