Wacol Distribution Centre, Cladding & Roofing
Walz Group · Wacol
Issued 4 Jul 2026 · closes 22 Aug 2026 · valid 60 days · Priya Raghavan
Price, ex GST
$1,460,526
Cost build-up
$1,184,131
Margin
$276,395 19%
Markup applied
20%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Estimate
Q32125
Valid 60 days from 4 Jul 2026
To
Walz Group
Tim Kessell, Operations Manager
tim.kessell@walz.com.au
ABN 31 093 462 088
Job
Wacol Distribution Centre, Cladding & Roofing
Wacol
Sector: Industrial
Estimate closes 22 Aug 2026
Scope of works
New KLIP-LOK 700 wall cladding and TRIMDEK roof sheeting to the distribution centre, flashings, personnel doors and sealant.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 1 item | $18,450.00 | $18,450.00 |
| RS-PRE-SUP Site supervision, leading hand | 64 day | $1,248.00 | $79,872.00 |
| RS-PRE-DEM Demobilisation & make good | 1 item | $7,420.00 | $7,420.00 |
| Wall cladding | |||
| RS-CLD-KL7 KLIP-LOK 700 wall cladding, install | 4,180 m² | $134.80 | $563,464.00 |
| RS-CLD-FLA Custom flashings, supply and install | 1,180 lm | $114.00 | $134,520.00 |
| RS-CLD-DOR Personnel access door in cladding, form and trim | 8 ea | $1,840.00 | $14,720.00 |
| Roofing | |||
| RS-ROF-TRM TRIMDEK roof sheeting, install | 3,240 m² | $97.80 | $316,872.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 3,240 m² | $39.60 | $128,304.00 |
| Height access | |||
| RS-HGT-EWP EWP hire & operator, 45ft boom | 68 day | $1,780.00 | $121,040.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 2,180 lm | $34.80 | $75,864.00 |
| Total, ex GST | $1,460,526.00 |
| GST at 10% | $146,052.60 |
| Total, inc GST | $1,606,578.60 |
Exclusions
- · Structural steel
- · Concrete works
- · Fire services penetrations
This tender is valid for 60 days from 4 Jul 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320