Price, ex GST

$1,460,526

Cost build-up

$1,184,131

Margin

$276,395 19%

Markup applied

20%

on the cost build-up

QClad

Roofing · Cladding · Acoustics

Estimate

Q32125

Valid 60 days from 4 Jul 2026

To

Walz Group

Tim Kessell, Operations Manager

tim.kessell@walz.com.au

ABN 31 093 462 088

Job

Wacol Distribution Centre, Cladding & Roofing

Wacol

Sector: Industrial

Estimate closes 22 Aug 2026

Scope of works

New KLIP-LOK 700 wall cladding and TRIMDEK roof sheeting to the distribution centre, flashings, personnel doors and sealant.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 1 item $18,450.00 $18,450.00
RS-PRE-SUP Site supervision, leading hand 64 day $1,248.00 $79,872.00
RS-PRE-DEM Demobilisation & make good 1 item $7,420.00 $7,420.00
Wall cladding
RS-CLD-KL7 KLIP-LOK 700 wall cladding, install 4,180 m² $134.80 $563,464.00
RS-CLD-FLA Custom flashings, supply and install 1,180 lm $114.00 $134,520.00
RS-CLD-DOR Personnel access door in cladding, form and trim 8 ea $1,840.00 $14,720.00
Roofing
RS-ROF-TRM TRIMDEK roof sheeting, install 3,240 m² $97.80 $316,872.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 3,240 m² $39.60 $128,304.00
Height access
RS-HGT-EWP EWP hire & operator, 45ft boom 68 day $1,780.00 $121,040.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 2,180 lm $34.80 $75,864.00
Total, ex GST$1,460,526.00
GST at 10%$146,052.60
Total, inc GST$1,606,578.60

Exclusions

  • · Structural steel
  • · Concrete works
  • · Fire services penetrations

This tender is valid for 60 days from 4 Jul 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320