Q32096 Demo Caloundra Sth West Primary School, Stage 2
Accounting connected Thu 13 Aug 2026
Q32096 Estimating - Submitted Commercial

Caloundra Sth West Primary School, Stage 2

Also priced for ADCO (Brisbane) and BADGE

Hutchinson Builders · Caloundra South

Issued 28 Oct 2025 · closes 27 Nov 2025 · valid 90 days · Priya Raghavan

Priced for three builders off the same set of drawings, so whoever wins the head contract QClad are in the price. The one to watch on the board.

Price, ex GST

$1,496,856

Cost build-up

$1,232,061

Margin

$264,795 18%

Markup applied

22%

on the cost build-up

Also priced for

The same package priced off the same drawings for ADCO Constructions and BADGE Constructions. Whoever wins the head contract, QClad are in the price.

QClad

Roofing · Cladding · Acoustics

Estimate

Q32096

Valid 90 days from 28 Oct 2025

To

Hutchinson Builders

Danielle Whyte, Contracts Administrator

dwhyte@hutchinsonbuilders.com.au

ABN 27 009 778 129

Job

Caloundra Sth West Primary School, Stage 2

Caloundra South

Sector: Commercial

Estimate closes 27 Nov 2025

Scope of works

Roof and wall cladding to Blocks C and D: KLIP-LOK 406 roof, Fielders Finesse architectural cladding to the street elevations, CUSTOM ORB elsewhere, insulation, safety mesh, rainwater goods and permanent roof anchors.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 1 item $18,450.00 $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 1 item $2,680.00 $2,680.00
RS-PRE-IND Site induction & verification of competency 12 ea $585.00 $7,020.00
RS-PRE-SUP Site supervision, leading hand 86 day $1,248.00 $107,328.00
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle 1,180 m² $94.50 $111,510.00
RS-PRE-DEM Demobilisation & make good 1 item $7,420.00 $7,420.00
Roofing
RS-ROF-KL4 KLIP-LOK 406 roof sheeting, install 2,640 m² $116.40 $307,296.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 2,640 m² $39.60 $104,544.00
RS-ROF-SAF Safety mesh, install to purlins 2,640 m² $24.80 $65,472.00
RS-ROF-RDG Ridge capping & barge, supply and install 320 lm $146.00 $46,720.00
RS-ROF-GUT Box gutter, supply and install 240 lm $385.00 $92,400.00
RS-ROF-DWP Downpipe & rainhead, supply and install 26 ea $864.00 $22,464.00
Wall cladding
RS-CLD-FIN Fielders Finesse architectural cladding, install 680 m² $214.00 $145,520.00
RS-CLD-CUS CUSTOM ORB wall cladding, install 1,420 m² $102.40 $145,408.00
RS-CLD-FLA Custom flashings, supply and install 940 lm $114.00 $107,160.00
RS-CLD-CAP Corner & parapet capping, supply and install 520 lm $138.00 $71,760.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 24 ea $745.00 $17,880.00
RS-HGT-EWP EWP hire & operator, 45ft boom 42 day $1,780.00 $74,760.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 1,180 lm $34.80 $41,064.00
Total, ex GST$1,496,856.00
GST at 10%$149,685.60
Total, inc GST$1,646,541.60

Exclusions

  • · Structural steel and framing
  • · Windows, glazing and louvres
  • · Painting
  • · Works during term time outside the nominated holiday windows

This tender is valid for 90 days from 28 Oct 2025 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms BIF 15/25, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320