Caloundra Sth West Primary School, Stage 2
Also priced for ADCO (Brisbane) and BADGE
Hutchinson Builders · Caloundra South
Issued 28 Oct 2025 · closes 27 Nov 2025 · valid 90 days · Priya Raghavan
Priced for three builders off the same set of drawings, so whoever wins the head contract QClad are in the price. The one to watch on the board.
Price, ex GST
$1,496,856
Cost build-up
$1,232,061
Margin
$264,795 18%
Markup applied
22%
on the cost build-up
Also priced for
The same package priced off the same drawings for ADCO Constructions and BADGE Constructions. Whoever wins the head contract, QClad are in the price.
QClad
Roofing · Cladding · Acoustics
Estimate
Q32096
Valid 90 days from 28 Oct 2025
To
Hutchinson Builders
Danielle Whyte, Contracts Administrator
dwhyte@hutchinsonbuilders.com.au
ABN 27 009 778 129
Job
Caloundra Sth West Primary School, Stage 2
Caloundra South
Sector: Commercial
Estimate closes 27 Nov 2025
Scope of works
Roof and wall cladding to Blocks C and D: KLIP-LOK 406 roof, Fielders Finesse architectural cladding to the street elevations, CUSTOM ORB elsewhere, insulation, safety mesh, rainwater goods and permanent roof anchors.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 1 item | $18,450.00 | $18,450.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 1 item | $2,680.00 | $2,680.00 |
| RS-PRE-IND Site induction & verification of competency | 12 ea | $585.00 | $7,020.00 |
| RS-PRE-SUP Site supervision, leading hand | 86 day | $1,248.00 | $107,328.00 |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | 1,180 m² | $94.50 | $111,510.00 |
| RS-PRE-DEM Demobilisation & make good | 1 item | $7,420.00 | $7,420.00 |
| Roofing | |||
| RS-ROF-KL4 KLIP-LOK 406 roof sheeting, install | 2,640 m² | $116.40 | $307,296.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 2,640 m² | $39.60 | $104,544.00 |
| RS-ROF-SAF Safety mesh, install to purlins | 2,640 m² | $24.80 | $65,472.00 |
| RS-ROF-RDG Ridge capping & barge, supply and install | 320 lm | $146.00 | $46,720.00 |
| RS-ROF-GUT Box gutter, supply and install | 240 lm | $385.00 | $92,400.00 |
| RS-ROF-DWP Downpipe & rainhead, supply and install | 26 ea | $864.00 | $22,464.00 |
| Wall cladding | |||
| RS-CLD-FIN Fielders Finesse architectural cladding, install | 680 m² | $214.00 | $145,520.00 |
| RS-CLD-CUS CUSTOM ORB wall cladding, install | 1,420 m² | $102.40 | $145,408.00 |
| RS-CLD-FLA Custom flashings, supply and install | 940 lm | $114.00 | $107,160.00 |
| RS-CLD-CAP Corner & parapet capping, supply and install | 520 lm | $138.00 | $71,760.00 |
| Height access | |||
| RS-HGT-ANC Roof anchor point: supply, install & certify | 24 ea | $745.00 | $17,880.00 |
| RS-HGT-EWP EWP hire & operator, 45ft boom | 42 day | $1,780.00 | $74,760.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 1,180 lm | $34.80 | $41,064.00 |
| Total, ex GST | $1,496,856.00 |
| GST at 10% | $149,685.60 |
| Total, inc GST | $1,646,541.60 |
Exclusions
- · Structural steel and framing
- · Windows, glazing and louvres
- · Painting
- · Works during term time outside the nominated holiday windows
This tender is valid for 90 days from 28 Oct 2025 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms BIF 15/25, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.