Q32364 Demo Groote Island, Flo Jo's
Accounting connected Thu 13 Aug 2026
Q32364 Estimating - Submitted Mining & Resources 21/7 · 8 crew · 6 trips

Groote Island, Flo Jo's

Replacement of structural elements, purlins and roofing to multiple structures

Groote Eylandt Mining Company · Groote Eylandt, NT

Issued 14 May 2026 · closes 13 Jun 2026 · valid 120 days · Dylan Fraser

Lodged 13 Jun 2026, no answer yet. Gemco's capital release is the hold-up rather than the price.

Price, ex GST

$1,626,630

Cost build-up

$1,316,662

Margin

$309,968 19%

Markup applied

27%

on the cost build-up

Roster and travel priced in

FIFO work is priced on the roster, not on a day rate. The trips are part of the number.

Swing

21 on, 7 off

Crew allocated

8

Trips required

6

Work hours per day

10

Roster days on

21

Cycles

3

QClad

Roofing · Cladding · Acoustics

Estimate

Q32364

Valid 120 days from 14 May 2026

To

Groote Eylandt Mining Company

Warrick Delaney, Superintendent, Fixed Plant

w.delaney@gemco.com.au

ABN 51 009 265 006

Job

Groote Island, Flo Jo's

Groote Eylandt, NT

Sector: Mining & Resources

Estimate closes 13 Jun 2026

Scope of works

Replace corroded structural elements and purlins and re-roof the Flo Jo's accommodation and messing structures, including safety mesh, rainwater goods and a permanent access system.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 2 item $18,450.00 $36,900.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 2 item $2,680.00 $5,360.00
RS-PRE-IND Site induction & verification of competency 14 ea $585.00 $8,190.00
RS-PRE-SUP Site supervision, leading hand 124 day $1,248.00 $154,752.00
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle 940 m² $94.50 $88,830.00
RS-PRE-DEM Demobilisation & make good 2 item $7,420.00 $14,840.00
Roofing
RS-ROF-STR Strip existing roof sheeting & dispose 2,640 m² $52.40 $138,336.00
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 2,640 m² $141.80 $374,352.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 2,640 m² $39.60 $104,544.00
RS-ROF-SAF Safety mesh, install to purlins 2,640 m² $24.80 $65,472.00
RS-ROF-RDG Ridge capping & barge, supply and install 320 lm $146.00 $46,720.00
RS-ROF-GUT Box gutter, supply and install 218 lm $385.00 $83,930.00
RS-ROF-DWP Downpipe & rainhead, supply and install 24 ea $864.00 $20,736.00
Wall cladding
RS-CLD-CUS CUSTOM ORB wall cladding, install 1,180 m² $102.40 $120,832.00
RS-CLD-FLA Custom flashings, supply and install 860 lm $114.00 $98,040.00
Height access
RS-HGT-ANC Roof anchor point: supply, install & certify 28 ea $745.00 $20,860.00
RS-HGT-STA Static line system: supply, install & certify 240 lm $286.00 $68,640.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 1,320 lm $34.80 $45,936.00
Labour & plant
RS-LAB-TRV Travel & living away: per person, per day 336 day $385.00 $129,360.00
Total, ex GST$1,626,630.00
GST at 10%$162,663.00
Total, inc GST$1,789,293.00

Exclusions

  • · Barge freight
  • · Internal fit-out
  • · Accommodation, by Gemco
  • · Structural design and certification

This tender is valid for 120 days from 14 May 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.