QCLNG Train 2: Acoustic Enclosure Refit
Australia Pacific LNG · Curtis Island, Gladstone, QLD · contract APL-T2-TA26-3390
Marcus Deng · 15 Sep 2026 → 28 Nov 2026
Held pending the turnaround date moving. Hot-work permits and gas test before every cut; one calibrated 4-head detector per crew. Barge access only.
The position
Every figure below is the sum of rows on this page.
Contract sum
$1,156,242
- Tendered
- $1,156,242
- Approved variations
- +$0
Work in place
$2,680
- Complete
- 0.2%
- Still to run
- $1,153,562
Claimed & certified
$0
- Certified
- $0
- Unclaimed WIP
- $2,680
- Retention held
- $0
Margin
$392 14.6%
- Cost of work in place
- $2,288
- Against the build-up
- $0
- Committed, not received
- $0
Cost centres
Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.
| Cost centre | Value | Earned | % | Budget hrs | Actual hrs | Budget material | Actual material | Committed | Run | Margin |
|---|---|---|---|---|---|---|---|---|---|---|
| CC-01 Preliminaries & establishment 4 tasks · General | $35,570 | $2,680 | 8% | 210 | 22 | $0 | $0 | - | $0 | 15% |
| CC-04 Acoustics 5 tasks · General | $1,005,232 | $0 | 0% | 2,682.4 | 0 | $0 | $0 | - | $0 | 0% |
| CC-05 Height access & safety systems 1 task · General | $115,440 | $0 | 0% | 780 | 0 | $0 | $0 | - | $0 | 0% |
| Job total | $1,156,242 | $2,680 | 0% | 3,672.4 | 22 | $0 | $0 | $0 | $0 | 15% |
The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $2,288, which is the job's actual cost.
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Mobilisation & site establishment RS-PRE-MOB | General | 1 item | 0 | 0% | $18,450 | $0 | 0 of 96 |
| Demobilisation & make good RS-PRE-DEM | General | 1 item | 0 | 0% | $7,420 | $0 | 0 of 44 |
| Site induction & verification of competency RS-PRE-IND | General | 12 ea | 0 | 0% | $7,020 | $0 | 0 of 48 |
| SWMS, JSA & site-specific safety plan RS-PRE-SWM | General | 1 item | 1 | 100% | $2,680 | $2,680 | 22 of 22 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Acoustic absorption panel, install RS-ACO-PNL | General | 1,480 m² | 0 | 0% | $338,920 | $0 | 0 of 917.6 |
| Plant acoustic enclosure, fabricate and install RS-ACO-ENC | General | 620 m² | 0 | 0% | $298,840 | $0 | 0 of 818.4 |
| Mass-loaded acoustic barrier mat, install RS-ACO-BAR | General | 1,480 m² | 0 | 0% | $230,880 | $0 | 0 of 621.6 |
| Isophonic bracket & resilient mount system RS-ACO-ISO | General | 1,480 m² | 0 | 0% | $132,312 | $0 | 0 of 310.8 |
| Post-installation acoustic verification test RS-ACO-TST | General | 1 item | 0 | 0% | $4,280 | $0 | 0 of 14 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Rope access technician, IRATA RS-HGT-ROP | General | 78 day | 0 | 0% | $115,440 | $0 | 0 of 780 |
Schedule of rates
Contract quantity, measured to date, and what each line is worth. Lines added by a variation carry its number.
| Rate | Rate, ex GST | Qty | Measured | Contract value | In place | Cost of it | Margin |
|---|---|---|---|---|---|---|---|
| Preliminaries | |||||||
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 1 | 0 0% | $18,450 | $0 | $0 | - |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | $2,680.00/item | 1 | 1 100% | $2,680 | $2,680 | $2,288 | 15% |
| RS-PRE-IND Site induction & verification of competency | $585.00/ea | 12 | 0 0% | $7,020 | $0 | $0 | - |
| RS-PRE-DEM Demobilisation & make good | $7,420.00/item | 1 | 0 0% | $7,420 | $0 | $0 | - |
| Acoustics | |||||||
| RS-ACO-ENC Plant acoustic enclosure, fabricate and install | $482.00/m² | 620 | 0 0% | $298,840 | $0 | $0 | - |
| RS-ACO-PNL Acoustic absorption panel, install | $229.00/m² | 1,480 | 0 0% | $338,920 | $0 | $0 | - |
| RS-ACO-BAR Mass-loaded acoustic barrier mat, install | $156.00/m² | 1,480 | 0 0% | $230,880 | $0 | $0 | - |
| RS-ACO-ISO Isophonic bracket & resilient mount system | $89.40/m² | 1,480 | 0 0% | $132,312 | $0 | $0 | - |
| RS-ACO-TST Post-installation acoustic verification test | $4,280.00/item | 1 | 0 0% | $4,280 | $0 | $0 | - |
| Height access | |||||||
| RS-HGT-ROP Rope access technician, IRATA | $1,480.00/day | 78 | 0 0% | $115,440 | $0 | $0 | - |
| Total | $1,156,242 | $2,680 | $2,288 | 15% | |||
Variations
An approved variation's lines join the schedule of rates above on approval.
| No. | Variation | Raised | Their ref | Value, ex GST | Built | Status |
|---|---|---|---|---|---|---|
| No variations on this contract. | ||||||
Progress claims
Lodged under the QLD BIF Act: 15 business days to a payment schedule, 25 to payment. Retention at 5%.
| Claim | Period | This claim, ex GST | Retention | Inc GST | Lodged | Invoice | Status |
|---|---|---|---|---|---|---|---|
| Nothing claimed on this contract yet. | |||||||
Labour booked this week
0 hours, $0.00 of cost, off the crew app. 42 hours on this job to date.
| Day card | Person | Date | Task | Rate | Hours | Cost | Status |
|---|---|---|---|---|---|---|---|
| No hours booked to this job this week. | |||||||
Purchase orders
$0.00 committed and not yet received.
| PO | Supplier | Deliver to | Raised | Expected | Ex GST | Status |
|---|---|---|---|---|---|---|
| Nothing ordered against this job. | ||||||
Nothing recorded against this job yet.
Correspondence
RFIs, material approvals and anything else sent about QJ2050, with the replies on the same thread.
Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.