QJ1809 Demo Rio Tinto Boyne Smelters: Potline Cladding
Accounting connected Thu 13 Aug 2026
QJ1809 Complete Mining & Resources

Rio Tinto Boyne Smelters: Potline Cladding

Rio Tinto Aluminium · Boyne Island, Gladstone, QLD · contract RTA-BSL-PL-2022-3318

Marcus Deng · 7 Feb 2023 → 1 Apr 2023 · PC 13 Apr 2023 · DLP ends 13 Apr 2024

Client view

The position

Every figure below is the sum of rows on this page.

Contract sum

$430,590

Tendered
$430,590
Approved variations
+$0

Work in place

$430,590

Complete
100.0%
Still to run
$0

Claimed & certified

$430,590

Certified
$52,532
Unclaimed WIP
$0
Retention held
$0

Margin

$78,299 18.2%

Cost of work in place
$352,291
Against the build-up
-$6,200
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 3 tasks · General $78,286 $78,286 100% 581 560.5 $0 -$366 - -$2,289 20%
CC-03 Wall cladding 2 tasks · General $223,480 $223,480 100% 843.6 828.2 $61,346 $59,969 - -$2,820 15%
CC-05 Height access & safety systems 1 task · General $94,720 $94,720 100% 640 634.4 $0 -$124 - -$654 22%
CC-06 Weatherproofing 1 task · General $34,104 $34,104 100% 196 192.1 $1,921 $1,852 - -$437 22%
Job total $430,590 $430,590 100% 2,260.6 2,215.2 $63,267 $61,331 $0 -$6,200 18%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $352,291, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$78,286 of $78,286 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 42 day 42 100% $52,416 $52,416 441 of 441
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$223,480 of $223,480 · 100%
TaskSub-jobContractDone%ValueEarnedHours
CUSTOM ORB wall cladding, install RS-CLD-CUS General 1,480 m² 1,480 100% $151,552 $151,552 444 of 444
Strip existing wall cladding & dispose RS-CLD-STR General 1,480 m² 1,480 100% $71,928 $71,928 399.6 of 399.6
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$94,720 of $94,720 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Rope access technician, IRATA RS-HGT-ROP General 64 day 64 100% $94,720 $94,720 640 of 640
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$34,104 of $34,104 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 980 lm 980 100% $34,104 $34,104 196 of 196

Correspondence

RFIs, material approvals and anything else sent about QJ1809, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.