RTAY Yarwun Central Workshop: Cladding
Rio Tinto Aluminium · Yarwun, Gladstone, QLD · contract RTA-YAR-CW-2024-5518
Cameron Hale · 15 Oct 2024 → 5 Apr 2025 · PC 12 Apr 2025 · DLP ends 12 Apr 2026
The position
Every figure below is the sum of rows on this page.
Contract sum
$897,150
- Tendered
- $897,150
- Approved variations
- +$0
Work in place
$897,150
- Complete
- 100.0%
- Still to run
- $0
Claimed & certified
$897,150
- Certified
- $104,069
- Unclaimed WIP
- $0
- Retention held
- $0
Margin
$164,227 18.3%
- Cost of work in place
- $732,923
- Against the build-up
- -$16,400
- Committed, not received
- $0
Cost centres
Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.
| Cost centre | Value | Earned | % | Budget hrs | Actual hrs | Budget material | Actual material | Committed | Run | Margin |
|---|---|---|---|---|---|---|---|---|---|---|
| CC-01 Preliminaries & establishment 4 tasks · General | $142,714 | $142,714 | 100% | 1,112 | 1,061.4 | $0 | -$625 | - | -$5,380 | 21% |
| CC-02 Roofing 1 task · General | $115,404 | $115,404 | 100% | 354 | 347.3 | $46,339 | $45,494 | - | -$1,470 | 17% |
| CC-03 Wall cladding 3 tasks · General | $471,600 | $471,600 | 100% | 1,722.4 | 1,681.9 | $137,786 | $133,973 | - | -$7,618 | 16% |
| CC-05 Height access & safety systems 1 task · General | $110,360 | $110,360 | 100% | 620 | 612.9 | $0 | -$324 | - | -$987 | 22% |
| CC-06 Weatherproofing 1 task · General | $57,072 | $57,072 | 100% | 328 | 319.5 | $3,214 | $3,067 | - | -$945 | 22% |
| Job total | $897,150 | $897,150 | 100% | 4,136.4 | 4,023 | $187,339 | $181,584 | $0 | -$16,400 | 18% |
The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $732,923, which is the job's actual cost.
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Site supervision, leading hand RS-PRE-SUP | General | 88 day | 88 | 100% | $109,824 | $109,824 | 924 of 924 |
| Mobilisation & site establishment RS-PRE-MOB | General | 1 item | 1 | 100% | $18,450 | $18,450 | 96 of 96 |
| Demobilisation & make good RS-PRE-DEM | General | 1 item | 1 | 100% | $7,420 | $7,420 | 44 of 44 |
| Site induction & verification of competency RS-PRE-IND | General | 12 ea | 12 | 100% | $7,020 | $7,020 | 48 of 48 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| TRIMDEK roof sheeting, install RS-ROF-TRM | General | 1,180 m² | 1,180 | 100% | $115,404 | $115,404 | 354 of 354 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| CUSTOM ORB wall cladding, install RS-CLD-CUS | General | 2,640 m² | 2,640 | 100% | $270,336 | $270,336 | 792 of 792 |
| Strip existing wall cladding & dispose RS-CLD-STR | General | 2,640 m² | 2,640 | 100% | $128,304 | $128,304 | 712.8 of 712.8 |
| Custom flashings, supply and install RS-CLD-FLA | General | 640 lm | 640 | 100% | $72,960 | $72,960 | 217.6 of 217.6 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| EWP hire & operator, 45ft boom RS-HGT-EWP | General | 62 day | 62 | 100% | $110,360 | $110,360 | 620 of 620 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Sealant to laps, penetrations & flashings RS-WPF-SEA | General | 1,640 lm | 1,640 | 100% | $57,072 | $57,072 | 328 of 328 |
Schedule of rates
Contract quantity, measured to date, and what each line is worth. Lines added by a variation carry its number.
| Rate | Rate, ex GST | Qty | Measured | Contract value | In place | Cost of it | Margin |
|---|---|---|---|---|---|---|---|
| Preliminaries | |||||||
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 1 | 1 100% | $18,450 | $18,450 | $15,224 | 17% |
| RS-PRE-IND Site induction & verification of competency | $585.00/ea | 12 | 12 100% | $7,020 | $7,020 | $5,652 | 19% |
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 88 | 88 100% | $109,824 | $109,824 | $91,080 | 17% |
| RS-PRE-DEM Demobilisation & make good | $7,420.00/item | 1 | 1 100% | $7,420 | $7,420 | $6,316 | 15% |
| Wall cladding | |||||||
| RS-CLD-STR Strip existing wall cladding & dispose | $48.60/m² | 2,640 | 2,640 100% | $128,304 | $128,304 | $118,774 | 7% |
| RS-CLD-CUS CUSTOM ORB wall cladding, install | $102.40/m² | 2,640 | 2,640 100% | $270,336 | $270,336 | $224,004 | 17% |
| RS-CLD-FLA Custom flashings, supply and install | $114.00/lm | 640 | 640 100% | $72,960 | $72,960 | $59,200 | 19% |
| Roofing | |||||||
| RS-ROF-TRM TRIMDEK roof sheeting, install | $97.80/m² | 1,180 | 1,180 100% | $115,404 | $115,404 | $96,961 | 16% |
| Height access | |||||||
| RS-HGT-EWP EWP hire & operator, 45ft boom | $1,780.00/day | 62 | 62 100% | $110,360 | $110,360 | $86,800 | 21% |
| Weatherproofing | |||||||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 1,640 | 1,640 100% | $57,072 | $57,072 | $45,313 | 21% |
| Total | $897,150 | $897,150 | $749,323 | 16% | |||
Variations
An approved variation's lines join the schedule of rates above on approval.
| No. | Variation | Raised | Their ref | Value, ex GST | Built | Status |
|---|---|---|---|---|---|---|
| No variations on this contract. | ||||||
Progress claims
Lodged under the QLD BIF Act: 15 business days to a payment schedule, 25 to payment. Retention at 5%.
| Claim | Period | This claim, ex GST | Retention | Inc GST | Lodged | Invoice | Status |
|---|---|---|---|---|---|---|---|
| PC-2025-0061No. 1 | May 2025 | $104,069.40 | $5,203.47 | $108,752.52 | 20 Apr 2025 | INV-25-0164 | Paid |
Invoices
| Invoice | Issued | Due | Inc GST | Ledger | Status |
|---|---|---|---|---|---|
| INV-25-0164 | 6 May 2025 | 23 May 2025 | $108,752.52 | XRO-4137 | Paid |
Labour booked this week
0 hours, $0.00 of cost, off the crew app. 4,218 hours on this job to date.
| Day card | Person | Date | Task | Rate | Hours | Cost | Status |
|---|---|---|---|---|---|---|---|
| No hours booked to this job this week. | |||||||
Purchase orders
$0.00 committed and not yet received.
| PO | Supplier | Deliver to | Raised | Expected | Ex GST | Status |
|---|---|---|---|---|---|---|
| Nothing ordered against this job. | ||||||
Nothing recorded against this job yet.
Correspondence
RFIs, material approvals and anything else sent about QJ1924, with the replies on the same thread.
Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.