QJ1924 Demo RTAY Yarwun Central Workshop: Cladding
Accounting connected Thu 13 Aug 2026
QJ1924 Complete Mining & Resources

RTAY Yarwun Central Workshop: Cladding

Rio Tinto Aluminium · Yarwun, Gladstone, QLD · contract RTA-YAR-CW-2024-5518

Cameron Hale · 15 Oct 2024 → 5 Apr 2025 · PC 12 Apr 2025 · DLP ends 12 Apr 2026

Client view

The position

Every figure below is the sum of rows on this page.

Contract sum

$897,150

Tendered
$897,150
Approved variations
+$0

Work in place

$897,150

Complete
100.0%
Still to run
$0

Claimed & certified

$897,150

Certified
$104,069
Unclaimed WIP
$0
Retention held
$0

Margin

$164,227 18.3%

Cost of work in place
$732,923
Against the build-up
-$16,400
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 4 tasks · General $142,714 $142,714 100% 1,112 1,061.4 $0 -$625 - -$5,380 21%
CC-02 Roofing 1 task · General $115,404 $115,404 100% 354 347.3 $46,339 $45,494 - -$1,470 17%
CC-03 Wall cladding 3 tasks · General $471,600 $471,600 100% 1,722.4 1,681.9 $137,786 $133,973 - -$7,618 16%
CC-05 Height access & safety systems 1 task · General $110,360 $110,360 100% 620 612.9 $0 -$324 - -$987 22%
CC-06 Weatherproofing 1 task · General $57,072 $57,072 100% 328 319.5 $3,214 $3,067 - -$945 22%
Job total $897,150 $897,150 100% 4,136.4 4,023 $187,339 $181,584 $0 -$16,400 18%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $732,923, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$142,714 of $142,714 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 88 day 88 100% $109,824 $109,824 924 of 924
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
Site induction & verification of competency RS-PRE-IND General 12 ea 12 100% $7,020 $7,020 48 of 48
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$115,404 of $115,404 · 100%
TaskSub-jobContractDone%ValueEarnedHours
TRIMDEK roof sheeting, install RS-ROF-TRM General 1,180 m² 1,180 100% $115,404 $115,404 354 of 354
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$471,600 of $471,600 · 100%
TaskSub-jobContractDone%ValueEarnedHours
CUSTOM ORB wall cladding, install RS-CLD-CUS General 2,640 m² 2,640 100% $270,336 $270,336 792 of 792
Strip existing wall cladding & dispose RS-CLD-STR General 2,640 m² 2,640 100% $128,304 $128,304 712.8 of 712.8
Custom flashings, supply and install RS-CLD-FLA General 640 lm 640 100% $72,960 $72,960 217.6 of 217.6
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$110,360 of $110,360 · 100%
TaskSub-jobContractDone%ValueEarnedHours
EWP hire & operator, 45ft boom RS-HGT-EWP General 62 day 62 100% $110,360 $110,360 620 of 620
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$57,072 of $57,072 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 1,640 lm 1,640 100% $57,072 $57,072 328 of 328

Correspondence

RFIs, material approvals and anything else sent about QJ1924, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.