This is what Saipem Clough Joint Venture see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewPROJECT CERES - UREA SHEDS
Ceres urea plant, Karratha, WA · your contract SCJV-CER-SC-1180
24 Feb 2026 to 3 Apr 2027 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$7,497,478
original $7,253,190 plus 2 approved variations
Work in place
$3,367,317
45% of the contract
Certified to date
$3,023,851
5 claims certified
Retention held
$151,193
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$711,892 of $1,222,328
$588,834 of $1,287,552
$437,547 of $1,305,404
$329,010 of $1,218,624
$175,442 of $364,992
$1,124,592 of $2,098,578
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0162 | 2026-07 | 8 Aug 2026 | $787,952 | $787,952 | 28 Aug 2026 | 11 Sep 2026 | Certified |
| PC-2026-0157 | 2026-06 | 8 Jul 2026 | $579,179 | $579,179 | 29 Jul 2026 | 12 Aug 2026 | Paid |
| PC-2026-0153 | 2026-05 | 6 Jun 2026 | $585,913 | $585,913 | 26 Jun 2026 | 10 Jul 2026 | Paid |
| PC-2026-0151 | 2026-04 | 8 May 2026 | $582,546 | $582,546 | 29 May 2026 | 12 Jun 2026 | Paid |
| PC-2026-0150 | 2026-03 | 8 Apr 2026 | $488,261 | $488,261 | 29 Apr 2026 | 13 May 2026 | Paid |
Variations
2 approved and in the contract sum above. 1 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-006-03 | Conveyor gallery access platform, additional static line The gallery walkway was extended 46m during construction and the original static line no longer reaches the far end. | SCJV-VO-0271 | 29 Jul 2026 | $42,952 | Submitted |
| VAR-006-02 | Cyclone tie-down upgrade, both sheds Region D wind classification confirmed after award. Fastener pattern and clip spacing both change, which is a quantity change rather than a rate change. | SCJV-VO-0246 | 3 Jun 2026 | $141,496 | Approved 23 Jun 2026, Dean Marchetti |
| VAR-006-01 | Additional roof lighting to Shed 1 SCJV instruction after the lighting design was revised; the shed was too dark to work in with the original sheet layout. | SCJV-VO-0218 | 22 Apr 2026 | $102,792 | Approved 12 May 2026, Dean Marchetti |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- QJ2006 Shed 1 roof sheeting layout DOC-4412 · Drawing · updated 9 Aug 2026 Rev D
- QJ2006 Project HSE Management Plan DOC-4404 · Safety plan · updated 31 May 2026 Rev B
- SCJV subcontract SCJV-CER-SC-1180, executed DOC-4401 · Contract · updated 5 Feb 2026 Rev 1
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- No inspection plans on this job.