QJ2006, client view Demo Saipem Clough Joint Venture
Accounting connected Thu 13 Aug 2026

This is what Saipem Clough Joint Venture see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.

Back to QClad's view
QJ2006 On site

PROJECT CERES - UREA SHEDS

Ceres urea plant, Karratha, WA · your contract SCJV-CER-SC-1180

24 Feb 2026 to 3 Apr 2027 · QClad contact Marcus Deng, 0411 748 902

Your subcontractor

QClad Services Pty Ltd

ABN 62 138 704 915 · QBCC 1174 320

Contract sum

$7,497,478

original $7,253,190 plus 2 approved variations

Work in place

$3,367,317

45% of the contract

Certified to date

$3,023,851

5 claims certified

Retention held

$151,193

5%, half released at PC

Progress by area

Measured on site, not estimated. This is the same measure the claim is built from.

Shed 1 north 58%

$711,892 of $1,222,328

Shed 1 south 46%

$588,834 of $1,287,552

Shed 2 north 34%

$437,547 of $1,305,404

Shed 2 south 27%

$329,010 of $1,218,624

Conveyor gallery 48%

$175,442 of $364,992

General 54%

$1,124,592 of $2,098,578

Progress claims

Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.

ClaimPeriodLodgedClaimed, ex GSTCertifiedSchedule duePayment dueStatus
PC-2026-0162 2026-07 8 Aug 2026 $787,952 $787,952 28 Aug 2026 11 Sep 2026 Certified
PC-2026-0157 2026-06 8 Jul 2026 $579,179 $579,179 29 Jul 2026 12 Aug 2026 Paid
PC-2026-0153 2026-05 6 Jun 2026 $585,913 $585,913 26 Jun 2026 10 Jul 2026 Paid
PC-2026-0151 2026-04 8 May 2026 $582,546 $582,546 29 May 2026 12 Jun 2026 Paid
PC-2026-0150 2026-03 8 Apr 2026 $488,261 $488,261 29 Apr 2026 13 May 2026 Paid

Variations

2 approved and in the contract sum above. 1 submitted and awaiting your determination.

VariationWhat and whyYour referenceRaisedValue, ex GSTStatus
VAR-006-03 Conveyor gallery access platform, additional static line The gallery walkway was extended 46m during construction and the original static line no longer reaches the far end. SCJV-VO-0271 29 Jul 2026 $42,952 Submitted
VAR-006-02 Cyclone tie-down upgrade, both sheds Region D wind classification confirmed after award. Fastener pattern and clip spacing both change, which is a quantity change rather than a rate change. SCJV-VO-0246 3 Jun 2026 $141,496 Approved 23 Jun 2026, Dean Marchetti
VAR-006-01 Additional roof lighting to Shed 1 SCJV instruction after the lighting design was revised; the shed was too dark to work in with the original sheet layout. SCJV-VO-0218 22 Apr 2026 $102,792 Approved 12 May 2026, Dean Marchetti

Documents issued to you

Current revision only. A superseded revision is never issued twice.

  • QJ2006 Shed 1 roof sheeting layout DOC-4412 · Drawing · updated 9 Aug 2026 Rev D
  • QJ2006 Project HSE Management Plan DOC-4404 · Safety plan · updated 31 May 2026 Rev B
  • SCJV subcontract SCJV-CER-SC-1180, executed DOC-4401 · Contract · updated 5 Feb 2026 Rev 1

Inspection and test plans

Hold points and witness points on your job, with what has been signed.

  • No inspection plans on this job.