PC-2026-0196 Demo PROJECT CERES - UREA SHEDS · Aug 2026
Accounting connected Thu 13 Aug 2026
PC-2026-0196 Draft Claim 6 · Aug 2026 QJ2006

Payment claim 6

PROJECT CERES - UREA SHEDS · Saipem Clough Joint Venture

August, open. Measures live against the resolved schedule of rates, so anything measured or approved today lands in this claim.

This claim is measuring live

It is the value of everything in place on QJ2006 less what claim 5 already claimed, so an approved variation moves it immediately. Lodging it freezes the amount, because a payment claim under the BIF Act is served at a stated figure, and starts the fifteen and twenty-five business-day clocks against Saipem Clough Joint Venture.

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0196

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

Saipem Clough Joint Venture

ABN 29 648 227 913

Dean Marchetti, Subcontracts Manager, Ceres

d.marchetti@scjv.com.au

Perth WA

Contract

SCJV-CER-SC-1180

PROJECT CERES - UREA SHEDS

Ceres urea plant, Karratha, WA

Reference date: 13 Aug 2026

Period: Aug 2026

Claim number: 6

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 6 item $110,700.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 6 item $16,080.00
RS-PRE-IND Site induction & verification of competency $585.00/ea 36.1 ea $21,118.50
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 169.84 day $211,960.32
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle $101.80/m² 1,856.4 m² $188,981.52
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 1,569.6 m² $82,247.04
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install $136.80/m² 2,969.6 m² $406,241.28
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install $136.80/m² 1,388.8 m² $189,987.84
RS-ROF-INS Roof insulation blanket 75mm R1.8, install $39.60/m² 2,969.6 m² $117,596.16
RS-ROF-INS Roof insulation blanket 75mm R1.8, install $39.60/m² 1,388.8 m² $54,996.48
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 3,072 m² $76,185.60
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 1,475.6 m² $36,594.88
RS-ROF-RDG Ridge capping & barge, supply and install $146.00/lm 362.44 lm $52,916.24
RS-ROF-GUT Box gutter, supply and install $385.00/lm 220.32 lm $84,823.20
RS-ROF-DWP Downpipe & rainhead, supply and install $864.00/ea 22.32 ea $19,284.48
RS-ROF-VNT Ridge ventilator, supply and install $624.00/lm 75.04 lm $46,824.96
RS-CLD-KSP Kingspan KS1000 RW insulated panel, install $289.40/m² 1,705.2 m² $493,484.88
RS-CLD-KSP Kingspan KS1000 RW insulated panel, install $289.40/m² 717.6 m² $207,673.44
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 836.4 lm $95,349.60
RS-CLD-CAP Corner & parapet capping, supply and install $138.00/lm 400.2 lm $55,227.60
RS-HGT-ANC Roof anchor point: supply, install & certify $745.00/ea 55.68 ea $41,481.60
RS-HGT-STA Static line system: supply, install & certify $286.00/lm 388.8 lm $111,196.80
RS-HGT-EWP EWP hire & operator, 45ft boom $1,780.00/day 87.42 day $155,607.60
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 851.2 lm $29,621.76
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 523.8 lm $18,228.24
RS-WPF-PEN Roof penetration flashing, form & seal $684.00/ea 33.28 ea $22,763.52
RS-LAB-TRV Travel & living away: per person, per day $385.00/day 545.6 day $210,056.00
RS-ROF-SKY Fibreglass roof lighting, install · VAR-006-01 Additional roof lighting to Shed 1 $198.00/m² 326.8 m² $64,706.40
RS-WPF-PEN Roof penetration flashing, form & seal · VAR-006-01 Additional roof lighting to Shed 1 $684.00/ea 20.64 ea $14,117.76
RS-WPF-SEA Sealant to laps, penetrations & flashings · VAR-006-01 Additional roof lighting to Shed 1 $34.80/lm 275.2 lm $9,576.96
RS-ROF-SAF Safety mesh, install to purlins · VAR-006-02 Cyclone tie-down upgrade, both sheds $24.80/m² 1,874.8 m² $46,495.04
RS-CLD-FLA Custom flashings, supply and install · VAR-006-02 Cyclone tie-down upgrade, both sheds $114.00/lm 412.8 lm $47,059.20
RS-WPF-SEA Sealant to laps, penetrations & flashings · VAR-006-02 Cyclone tie-down upgrade, both sheds $34.80/lm 808.4 lm $28,132.32
Value of work in place to date$3,367,317.22
Less previously claimed (claims 1-5)($3,023,850.86)
Value of work this claim, ex GST$343,466.36
Less retention at 5%($17,173.32)
Net, ex GST$326,293.04
GST at 10%$32,629.30
Amount claimed, inc GST$358,922.34

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before the due date for payment. Retention of $17,173.32 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0196

Claim history on QJ2006

Cumulative to date: $3,367,317.22 of a $7,497,478 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0162 Jul 2026 $787,952.23 8 Aug 2026 12 Aug 2026 - Certified
PC-2026-0157 Jun 2026 $579,178.56 8 Jul 2026 28 Jul 2026 11 Aug 2026 Paid
PC-2026-0153 May 2026 $585,913.19 6 Jun 2026 26 Jun 2026 22 Jul 2026 Paid
PC-2026-0151 Apr 2026 $582,545.88 8 May 2026 27 May 2026 23 Jun 2026 Paid
PC-2026-0150 Mar 2026 $488,261.00 8 Apr 2026 25 Apr 2026 22 May 2026 Paid