PC-2026-0184 Demo Boyne Smelters Stockpile Shed: Re-clad & Acoustics · Jul 2026
Accounting connected Wed 5 Aug 2026
PC-2026-0184 Overdue Claim 6 · Jul 2026 PRJ-2026-038

Payment claim 6

Boyne Smelters Stockpile Shed: Re-clad & Acoustics · Rio Tinto Aluminium

Sixteen business days since lodgement and no payment schedule from Rio Tinto. Under s.76 of the BIF Act they are now liable for the full claimed amount. The notice is drafted and awaiting director sign-off.

No payment schedule inside fifteen business days

Served 14 Jul 2026. The schedule was due 4 Aug 2026 and none has been received. Under s.76 of the BIF Act Rio Tinto Aluminium are now liable for the full claimed amount of $239,963.11 inc GST.

Served

14 Jul 2026

Payment schedule due

4 Aug 2026

15 business days

Certified

-

Payment due

18 Aug 2026

25 business days

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0184

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

Rio Tinto Aluminium

ABN 15 009 679 127

Grant Hollows, Superintendent, Fixed Plant

grant.hollows@riotinto.com

Boyne Island QLD

Contract

RTA-BSL-SC-88104

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Boyne Island, Gladstone, QLD

Reference date: 14 Jul 2026

Period: Jul 2026

Claim number: 6

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 item $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 item $2,680.00
RS-PRE-IND Site induction & verification of competency $585.00/ea 14 ea $8,190.00
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 93.22 day $116,338.56
RS-CLD-STR Strip existing wall cladding & dispose $48.60/m² 4,004.4 m² $194,613.84
RS-CLD-CUS CUSTOM ORB wall cladding, install $107.80/m² 3,663.6 m² $394,936.08
RS-ROF-TRM TRIMDEK roof sheeting, install $97.80/m² 1,710.8 m² $167,316.24
RS-ACO-PNL Acoustic absorption panel, install $229.00/m² 892.8 m² $204,451.20
RS-ACO-LIN Perforated acoustic liner tray, install $264.00/m² 567.6 m² $149,846.40
RS-ACO-BAR Mass-loaded acoustic barrier mat, install $156.00/m² 868 m² $135,408.00
RS-ACO-ISO Isophonic bracket & resilient mount system $89.40/m² 917.6 m² $82,033.44
RS-ACO-ENC Plant acoustic enclosure, fabricate and install $482.00/m² 182.4 m² $87,916.80
RS-HGT-ROP Rope access technician, IRATA $1,480.00/day 78.72 day $116,505.60
RS-HGT-STA Static line system: supply, install & certify $286.00/lm 281.6 lm $80,537.60
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 784 lm $89,376.00
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 2,032.8 lm $70,741.44
RS-WPF-MEM Liquid-applied weatherproof membrane $162.00/m² 231 m² $37,422.00
RS-ACO-ENC Plant acoustic enclosure, fabricate and install · VAR-038-01 Acoustic enclosure extended to the second transfer point $482.00/m² 82.56 m² $39,793.92
RS-ACO-BAR Mass-loaded acoustic barrier mat, install · VAR-038-01 Acoustic enclosure extended to the second transfer point $156.00/m² 154.8 m² $24,148.80
RS-ACO-ISO Isophonic bracket & resilient mount system · VAR-038-01 Acoustic enclosure extended to the second transfer point $89.40/m² 154.8 m² $13,839.12
RS-HGT-ROP Rope access technician, IRATA · VAR-038-02 Rope access in lieu of EWP, southern elevation $1,480.00/day 29.24 day $43,275.20
Value of work in place to date$1,984,657.33
Less previously claimed (claims 1-5)($1,755,027.56)
Value of work this claim, ex GST$229,629.77
Less retention at 5%($11,481.49)
Net, ex GST$218,148.28
GST at 10%$21,814.83
Amount claimed, inc GST$239,963.11

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 18 Aug 2026. Retention of $11,481.49 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0184

Claim history on PRJ-2026-038

Cumulative to date: $1,984,657.33 of a $2,650,824 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0180 Jun 2026 $315,740.94 30 Jun 2026 17 Jul 2026 3 Aug 2026 Paid
PC-2026-0174 May 2026 $389,550.51 29 May 2026 17 Jun 2026 24 Jul 2026 Paid
PC-2026-0168 Apr 2026 $424,405.03 30 Apr 2026 19 May 2026 25 Jun 2026 Paid
PC-2026-0161 Mar 2026 $395,701.31 31 Mar 2026 20 Apr 2026 27 May 2026 Paid
PC-2026-0154 Feb 2026 $229,629.77 27 Feb 2026 18 Mar 2026 24 Apr 2026 Paid