This is what Rio Tinto Aluminium see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewBoyne Smelters Stockpile Shed: Re-clad & Acoustics
Boyne Island, Gladstone, QLD · your contract RTA-BSL-SC-88104
17 Feb 2026 to 5 Sep 2026 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$2,650,824
original $2,542,100 plus 2 approved variations
Work in place
$2,050,266
77% of the contract
Certified to date
$1,755,028
5 claims certified
Retention held
$87,751
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$145,659 of $184,004
$167,316 of $183,864
$678,926 of $777,984
$737,438 of $1,093,180
$212,764 of $251,880
$108,163 of $159,912
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0184 | 2026-07 | 22 Jul 2026 | $229,630 | - | 12 Aug 2026 | 26 Aug 2026 | Overdue |
| PC-2026-0180 | 2026-06 | 8 Jul 2026 | $315,741 | $315,741 | 29 Jul 2026 | 12 Aug 2026 | Paid |
| PC-2026-0174 | 2026-05 | 6 Jun 2026 | $389,551 | $389,551 | 26 Jun 2026 | 10 Jul 2026 | Paid |
| PC-2026-0168 | 2026-04 | 8 May 2026 | $424,405 | $424,405 | 29 May 2026 | 12 Jun 2026 | Paid |
| PC-2026-0161 | 2026-03 | 8 Apr 2026 | $395,701 | $395,701 | 29 Apr 2026 | 13 May 2026 | Paid |
| PC-2026-0154 | 2026-02 | 7 Mar 2026 | $229,630 | $229,630 | 27 Mar 2026 | 10 Apr 2026 | Paid |
Variations
2 approved and in the contract sum above. 1 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-038-03 | Membrane to the western gutter run Existing box gutter found perforated; liquid membrane applied rather than replacement. | RTA-VO-4451 | 17 Jul 2026 | $29,088 | Submitted |
| VAR-038-02 | Rope access in lieu of EWP, southern elevation EWP could not be positioned over the live conveyor; work reverted to rope access. | RTA-VO-4429 | 27 May 2026 | $18,280 | Approved 11 Jun 2026, Grant Hollows |
| VAR-038-01 | Acoustic enclosure extended to the second transfer point Rio Tinto's acoustic consultant required the enclosure extended after a boundary reading failed. | RTA-VO-4417 | 28 Apr 2026 | $90,444 | Approved 19 May 2026, Grant Hollows |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- Acoustic enclosure, transfer tower ITP-038-01 2 of 5 signed
- Weatherproofing, stockpile shed western wall ITP-038-02 1 of 3 signed