PC-2026-0168 Demo Boyne Smelters Stockpile Shed: Re-clad & Acoustics · Apr 2026
Accounting connected Wed 5 Aug 2026
PC-2026-0168 Paid Claim 3 · Apr 2026 PRJ-2026-038

Payment claim 3

Boyne Smelters Stockpile Shed: Re-clad & Acoustics · Rio Tinto Aluminium

Served

30 Apr 2026

Payment schedule due

21 May 2026

15 business days

Certified

19 May 2026

Payment due

4 Jun 2026

Paid 25 Jun 2026

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0168

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

Rio Tinto Aluminium

ABN 15 009 679 127

Grant Hollows, Superintendent, Fixed Plant

grant.hollows@riotinto.com

Boyne Island QLD

Contract

RTA-BSL-SC-88104

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Boyne Island, Gladstone, QLD

Reference date: 30 Apr 2026

Period: Apr 2026

Claim number: 3

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 item $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 item $2,680.00
RS-PRE-IND Site induction & verification of competency $585.00/ea 14 ea $8,190.00
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 93.22 day $116,338.56
RS-CLD-STR Strip existing wall cladding & dispose $48.60/m² 4,004.4 m² $194,613.84
RS-CLD-CUS CUSTOM ORB wall cladding, install $107.80/m² 3,663.6 m² $394,936.08
RS-ROF-TRM TRIMDEK roof sheeting, install $97.80/m² 1,710.8 m² $167,316.24
RS-ACO-PNL Acoustic absorption panel, install $229.00/m² 892.8 m² $204,451.20
RS-ACO-LIN Perforated acoustic liner tray, install $264.00/m² 567.6 m² $149,846.40
RS-ACO-BAR Mass-loaded acoustic barrier mat, install $156.00/m² 868 m² $135,408.00
RS-ACO-ISO Isophonic bracket & resilient mount system $89.40/m² 917.6 m² $82,033.44
RS-ACO-ENC Plant acoustic enclosure, fabricate and install $482.00/m² 182.4 m² $87,916.80
RS-HGT-ROP Rope access technician, IRATA $1,480.00/day 78.72 day $116,505.60
RS-HGT-STA Static line system: supply, install & certify $286.00/lm 281.6 lm $80,537.60
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 784 lm $89,376.00
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 2,032.8 lm $70,741.44
RS-WPF-MEM Liquid-applied weatherproof membrane $162.00/m² 231 m² $37,422.00
RS-ACO-ENC Plant acoustic enclosure, fabricate and install · VAR-038-01 Acoustic enclosure extended to the second transfer point $482.00/m² 82.56 m² $39,793.92
RS-ACO-BAR Mass-loaded acoustic barrier mat, install · VAR-038-01 Acoustic enclosure extended to the second transfer point $156.00/m² 154.8 m² $24,148.80
RS-ACO-ISO Isophonic bracket & resilient mount system · VAR-038-01 Acoustic enclosure extended to the second transfer point $89.40/m² 154.8 m² $13,839.12
RS-HGT-ROP Rope access technician, IRATA · VAR-038-02 Rope access in lieu of EWP, southern elevation $1,480.00/day 29.24 day $43,275.20
Value of work in place to date$1,049,736.11
Less previously claimed (claims 1-2)($625,331.08)
Value of work this claim, ex GST$424,405.03
Less retention at 5%($21,220.25)
Net, ex GST$403,184.78
GST at 10%$40,318.48
Amount claimed, inc GST$443,503.26

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 4 Jun 2026. Retention of $21,220.25 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0168

Claim history on PRJ-2026-038

Cumulative to date: $1,049,736.11 of a $2,650,824 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0161 Mar 2026 $395,701.31 31 Mar 2026 20 Apr 2026 27 May 2026 Paid
PC-2026-0154 Feb 2026 $229,629.77 27 Feb 2026 18 Mar 2026 24 Apr 2026 Paid