This is what Downer Rail see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewDowner Rail Maryborough: Periodic Roofing Works 2026
Downer Rail, Maryborough, QLD · your contract DWN-MBH-PER-2026
10 Feb 2026 to 26 Dec 2026 · QClad contact Cameron Hale, 0433 502 178
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$807,398
original $772,216 plus 2 approved variations
Work in place
$483,937
60% of the contract
Certified to date
$241,969
3 claims certified
Retention held
$12,098
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$69,489 of $119,808
$185,116 of $305,158
$24,898 of $47,880
$77,715 of $131,720
$52,049 of $92,808
$74,672 of $110,024
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0190 | 2026-07 | 8 Aug 2026 | $91,948 | - | 28 Aug 2026 | 11 Sep 2026 | Submitted |
| PC-2026-0183 | 2026-06 | 8 Jul 2026 | $97,271 | $97,271 | 29 Jul 2026 | 12 Aug 2026 | Paid |
| PC-2026-0175 | 2026-05 | 6 Jun 2026 | $79,850 | $79,850 | 26 Jun 2026 | 10 Jul 2026 | Paid |
| PC-2026-0164 | 2026-04 | 8 May 2026 | $64,848 | $64,848 | 29 May 2026 | 12 Jun 2026 | Paid |
PC-2026-0190, lodged 8 Aug 2026. A payment schedule has not been received. Under s.76 of the Act, a respondent who does not issue one inside the statutory period becomes liable for the full claimed amount.
Variations
2 approved and in the contract sum above. 1 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-046-03 | Shed 2 sheet replacement, 40 sheets Storm damage to the eastern slope, called off against the standing rates. | DWN-VO-0219 | 5 Aug 2026 | $17,120 | Submitted |
| VAR-046-02 | Shed 7 roof lighting replacement Called off against the standing rates after a hail event in June. | DWN-VO-0214 | 7 Jul 2026 | $16,632 | Approved 16 Jul 2026, Paul Mistry |
| VAR-046-01 | Shed 4 leak rectification, additional 60 hours Leak traced to a failed gutter joint rather than the sheet; scope grew on investigation. | DWN-VO-0208 | 14 May 2026 | $18,550 | Approved 27 May 2026, Paul Mistry |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- No inspection plans on this job.