This is what Laing O'Rourke Australia see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewQRSAUP: Brisbane Rail Stations Roofing & Cladding
Banyo, Buranda, Morningside & Lindum stations, QLD · your contract LOR-QRSAUP-SC-0442
16 Dec 2025 to 5 Dec 2026 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$4,093,279
original $3,919,150 plus 3 approved variations
Work in place
$2,499,553
61% of the contract
Certified to date
$2,384,573
8 claims certified
Retention held
$119,229
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$783,852 of $1,215,310
$922,423 of $1,459,321
$440,161 of $838,500
$255,804 of $395,000
$97,313 of $185,148
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0185 | 2026-07 | 8 Aug 2026 | $217,461 | $214,961 | 28 Aug 2026 | 11 Sep 2026 | Short certified |
| PC-2026-0181 | 2026-06 | 8 Jul 2026 | $344,938 | $344,938 | 29 Jul 2026 | 12 Aug 2026 | Paid |
| PC-2026-0176 | 2026-05 | 6 Jun 2026 | $369,934 | $369,934 | 26 Jun 2026 | 10 Jul 2026 | Paid |
| PC-2026-0170 | 2026-04 | 8 May 2026 | $354,937 | $354,937 | 29 May 2026 | 12 Jun 2026 | Paid |
| PC-2026-0163 | 2026-03 | 8 Apr 2026 | $324,942 | $324,942 | 29 Apr 2026 | 13 May 2026 | Paid |
| PC-2026-0156 | 2026-02 | 7 Mar 2026 | $302,446 | $302,446 | 27 Mar 2026 | 10 Apr 2026 | Paid |
| PC-2026-0149 | 2026-01 | 7 Feb 2026 | $267,452 | $267,452 | 27 Feb 2026 | 13 Mar 2026 | Paid |
| PC-2026-0142 | 2025-12 | 6 Jan 2026 | $204,963 | $204,963 | 27 Jan 2026 | 10 Feb 2026 | Paid |
Variations
3 approved and in the contract sum above. 1 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-041-04 | Lindum overpass: additional static line and anchor points Queensland Rail's height-safety review after the overpass was set required a continuous static line the full length of the deck and a further 18 certified anchors. Not in the tender scope; instructed on site 30 Jul 2026. | LOR-VO-0182 | 1 Aug 2026 | $85,239 | Submitted |
| VAR-041-03 | Architectural panel to Morningside entry, Finesse substitution Architect's instruction to substitute Fielders Finesse for the specified flat sheet on the entry elevation. | LOR-VO-0168 | 10 Jun 2026 | $48,268 | Approved 27 Jun 2026, Steve Bracken |
| VAR-041-02 | Extended possession, three additional night shutdowns QR granted three fewer possessions than programmed; the recovery required three additional night shifts. | LOR-VO-0141 | 16 Apr 2026 | $35,580 | Approved 2 May 2026, Steve Bracken |
| VAR-041-01 | Additional canopy sheeting, Banyo platform 2 Design change issued by Laing O'Rourke after the canopy was extended 14m to the south. | LOR-VO-0113 | 19 Feb 2026 | $90,281 | Approved 10 Mar 2026, Steve Bracken |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- QJ2041 Rail possession plan, August DOC-4376 · Report · updated 7 Aug 2026 Rev F
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- Roof sheeting, Banyo & Buranda canopies ITP-041-01 4 of 5 signed
- Static line and anchor system, Lindum overpass ITP-041-02 2 of 5 signed
- Architectural cladding, Morningside entry ITP-041-03 2 of 4 signed