This is what Mountain Creek State High School, Dept of Education see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewMountain Creek SHS: Hall Re-roof & Cladding
Mountain Creek, Sunshine Coast, QLD · your contract QED-MCSHS-2026-0331
7 Jul 2026 to 10 Oct 2026 · QClad contact Cameron Hale, 0433 502 178
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$967,046
original $945,534 plus 1 approved variation
Work in place
$460,403
48% of the contract
Certified to date
$252,301
1 claim certified
Retention held
$12,615
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$97,774 of $183,878
$272,957 of $589,656
$19,005 of $65,536
$51,060 of $65,744
$19,606 of $62,232
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0188 | 2026-07 | 8 Aug 2026 | $182,320 | - | 28 Aug 2026 | 11 Sep 2026 | Submitted |
| PC-2026-0182 | 2026-06 | 8 Jul 2026 | $252,301 | $252,301 | 29 Jul 2026 | 12 Aug 2026 | Paid |
PC-2026-0188, lodged 8 Aug 2026. A payment schedule has not been received. Under s.76 of the Act, a respondent who does not issue one inside the statutory period becomes liable for the full claimed amount.
Variations
1 approved and in the contract sum above. 1 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-047-02 | Additional edge protection to the covered walkway Department required guardrail to the walkway roof before any access, not in scope. | QED-VO-0117 | 29 Jul 2026 | $10,664 | Submitted |
| VAR-047-01 | Asbestos-containing sarking found, hold and dispose ACM sarking encountered under the existing sheets; hygienist engaged, works held eight days. | QED-VO-0114 | 21 Jul 2026 | $21,512 | Approved 1 Aug 2026, Ian Bardsley |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- Hall re-roof, Mountain Creek SHS ITP-047-01 2 of 5 signed