PC-2026-0188 Demo Mountain Creek SHS: Hall Re-roof & Cladding · Jul 2026
Accounting connected Wed 5 Aug 2026
PC-2026-0188 Submitted Claim 2 · Jul 2026 PRJ-2026-047

Payment claim 2

Mountain Creek SHS: Hall Re-roof & Cladding · Mountain Creek State High School, Dept of Education

Served

31 Jul 2026

Payment schedule due

21 Aug 2026

15 business days

Certified

-

Payment due

4 Sep 2026

25 business days

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0188

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

Mountain Creek State High School, Dept of Education

ABN 76 337 613 647

Ian Bardsley, Facilities Officer

ian.bardsley@qed.qld.gov.au

Mountain Creek QLD

Contract

QED-MCSHS-2026-0331

Mountain Creek SHS: Hall Re-roof & Cladding

Mountain Creek, Sunshine Coast, QLD

Reference date: 31 Jul 2026

Period: Jul 2026

Claim number: 2

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 item $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 item $2,680.00
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 27.88 day $34,794.24
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle $94.50/m² 352 m² $33,264.00
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 1,227.6 m² $64,326.24
RS-ROF-KL4 KLIP-LOK 406 roof sheeting, install $116.40/m² 871.2 m² $101,407.68
RS-ROF-INS Roof insulation blanket 75mm R1.8, install $39.60/m² 871.2 m² $34,499.52
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 990 m² $24,552.00
RS-ROF-RDG Ridge capping & barge, supply and install $146.00/lm 85.12 lm $12,427.52
RS-ROF-GUT Box gutter, supply and install $385.00/lm 53.76 lm $20,697.60
RS-ROF-DWP Downpipe & rainhead, supply and install $864.00/ea 5.94 ea $5,132.16
RS-CLD-CUS CUSTOM ORB wall cladding, install $102.40/m² 185.6 m² $19,005.44
RS-HGT-GRD Roof edge guardrail, install & hire $124.00/lm 339.68 lm $42,120.32
RS-HGT-ANC Roof anchor point: supply, install & certify $745.00/ea 12 ea $8,940.00
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 369.6 lm $12,862.08
RS-WPF-PEN Roof penetration flashing, form & seal $684.00/ea 9.86 ea $6,744.24
RS-PRE-SUP Site supervision, leading hand · VAR-047-01 Asbestos-containing sarking found, hold and dispose $1,248.00/day 6.88 day $8,586.24
RS-ROF-STR Strip existing roof sheeting & dispose · VAR-047-01 Asbestos-containing sarking found, hold and dispose $52.40/m² 189.2 m² $9,914.08
Value of work in place to date$434,620.77
Less previously claimed (claims 1-1)($137,200.20)
Value of work this claim, ex GST$297,420.57
Less retention at 5%($14,871.03)
Net, ex GST$282,549.54
GST at 10%$28,254.95
Amount claimed, inc GST$310,804.49

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 4 Sep 2026. Retention of $14,871.03 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0188

Claim history on PRJ-2026-047

Cumulative to date: $434,620.77 of a $967,046 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0182 Jun 2026 $137,200.20 30 Jun 2026 14 Jul 2026 30 Jul 2026 Paid