This is what Department of Defence, Estate & Infrastructure see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewWilliamtown RAAF: NACC Hangar Cladding Renewal
RAAF Base Williamtown, NSW · your contract DEF-EI-WLM-NACC-8804
22 Apr 2025 to 20 Dec 2025 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$1,795,916
original $1,593,424 plus 1 approved variation
Work in place
$1,790,610
100% of the contract
Certified to date
$91,321
1 claim certified
Retention held
$2,283
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$198,796 of $198,796
$1,274,416 of $1,274,416
$170,880 of $170,880
$143,904 of $143,904
$2,614 of $7,920
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0146 | 2025-12 | 27 Dec 2025 | $91,321 | $91,321 | 16 Jan 2026 | 30 Jan 2026 | Paid |
Variations
1 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-034-01 | Panel colour change, full northern elevation Defence changed the colour after 40% of the panel was on the wall. | DEF-VO-0918 | 27 Aug 2025 | $202,492 | Approved 17 Sep 2025, Maj. Ellen Straub |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- Hangar cladding renewal, Williamtown ITP-034-01 4 of 4 signed