Payment claim 9
Williamtown RAAF: NACC Hangar Cladding Renewal · Department of Defence, Estate & Infrastructure
Served
19 Dec 2025
Payment schedule due
9 Jan 2026
15 business days
Certified
14 Jan 2026
Payment due
23 Jan 2026
Paid 2 Feb 2026
QClad
Roofing · Cladding · Acoustics
Payment claim
PC-2026-0146
Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)
Claimant
QClad Services Pty Ltd
ABN 62 138 704 915
QBCC 1174 320
Unit 2/9-11 Lenco Cres, Landsborough QLD 4550
07 5474 4966 · admin@qclad.com
Respondent
Department of Defence, Estate & Infrastructure
ABN 68 706 814 312
Maj. Ellen Straub, Contract Administrator
ellen.straub@defence.gov.au
Canberra NSW
Contract
DEF-EI-WLM-NACC-8804
Williamtown RAAF: NACC Hangar Cladding Renewal
RAAF Base Williamtown, NSW
Reference date: 19 Dec 2025
Period: Dec 2025
Claim number: 9
Construction work carried out
| Item | Rate | Measured | Value, ex GST |
|---|---|---|---|
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 1 item | $18,450.00 |
| RS-PRE-IND Site induction & verification of competency | $585.00/ea | 14 ea | $8,190.00 |
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 132 day | $164,736.00 |
| RS-CLD-STR Strip existing wall cladding & dispose | $48.60/m² | 2,940 m² | $142,884.00 |
| RS-CLD-KSP Kingspan KS1000 RW insulated panel, install | $278.00/m² | 2,940 m² | $817,320.00 |
| RS-CLD-FLA Custom flashings, supply and install | $114.00/lm | 980 lm | $111,720.00 |
| RS-WPF-MEM Liquid-applied weatherproof membrane | $162.00/m² | 420 m² | $68,040.00 |
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 2,180 lm | $75,864.00 |
| RS-HGT-EWP EWP hire & operator, 45ft boom | $1,780.00/day | 96 day | $170,880.00 |
| RS-REC-DEF Defects-liability attendance | $1,320.00/day | 1.98 day | $2,613.60 |
| RS-PRE-DEM Demobilisation & make good | $7,420.00/item | 1 item | $7,420.00 |
| RS-CLD-KSP Kingspan KS1000 RW insulated panel, install · VAR-034-01 Panel colour change, full northern elevation | $278.00/m² | 620 m² | $172,360.00 |
| RS-CLD-STR Strip existing wall cladding & dispose · VAR-034-01 Panel colour change, full northern elevation | $48.60/m² | 620 m² | $30,132.00 |
| Value of work in place to date | $1,790,609.60 |
| Less previously claimed (claims 1-8) | ($1,699,288.51) |
| Value of work this claim, ex GST | $91,321.09 |
| Less retention at 5% | ($4,566.05) |
| Net, ex GST | $86,755.04 |
| GST at 10% | $8,675.50 |
| Amount claimed, inc GST | $95,430.54 |
This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 23 Jan 2026. Retention of $4,566.05 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.
Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915
Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0146