Bengalla VDC Re-roof Stage 2 · Bengalla Mining Company
Early works only: the permit regime, the survey and the first inductions. Crews mobilise 24 Aug.
This claim is measuring live
It is the value of everything in place on PRJ-2026-049 less what claim 0 already claimed, so an approved variation moves it immediately. Lodging it freezes the amount, because a payment claim under the BIF Act is served at a stated figure, and starts the fifteen and twenty-five business-day clocks against Bengalla Mining Company.
QClad
Roofing · Cladding · Acoustics
Payment claim
PC-2026-0194
Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)
Claimant
QClad Services Pty Ltd
ABN 62 138 704 915
QBCC 1174 320
Unit 2/9-11 Lenco Cres, Landsborough QLD 4550
07 5474 4966 · admin@qclad.com
Respondent
Bengalla Mining Company
ABN 12 010 715 555
Kate Mercer, Projects Superintendent
kate.mercer@bengalla.com.au
Muswellbrook NSW
Contract
BGA-VDC-S2-40118
Bengalla VDC Re-roof Stage 2
Bengalla Mine, Muswellbrook, NSW
Reference date: 5 Aug 2026
Period: Aug 2026
Claim number: 1
Construction work carried out
| Item | Rate | Measured | Value, ex GST |
|---|---|---|---|
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 0.35 item | $6,457.50 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | $2,680.00/item | 1 item | $2,680.00 |
| RS-PRE-IND Site induction & verification of competency | $585.00/ea | 7.92 ea | $4,633.20 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan · VAR-049-01 Early works, conveyor permit and survey | $2,680.00/item | 0.86 item | $2,304.80 |
| RS-PRE-SUP Site supervision, leading hand · VAR-049-01 Early works, conveyor permit and survey | $1,248.00/day | 5.16 day | $6,439.68 |
| Value of work in place to date | $22,515.18 |
| Less previously claimed (claims 1-0) | ($0.00) |
| Value of work this claim, ex GST | $22,515.18 |
| Less retention at 5% | ($1,125.76) |
| Net, ex GST | $21,389.42 |
| GST at 10% | $2,138.94 |
| Amount claimed, inc GST | $23,528.36 |
This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before the due date for payment. Retention of $1,125.76 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.
Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915
Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0194