This is what Queensland Rail see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewCoomera Station Re-roof
Coomera, Gold Coast, QLD · your contract QR-COO-RR-2024-7712
21 Jan 2025 to 24 May 2025 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$769,330
original $727,900 plus 2 approved variations
Work in place
$769,330
100% of the contract
Certified to date
$67,701
1 claim certified
Retention held
$0
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$295,686 of $295,686
$440,932 of $440,932
$32,712 of $32,712
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2025-0088 | 2025-07 | 1 Jun 2025 | $67,701 | $67,701 | 20 Jun 2025 | 4 Jul 2025 | Paid |
Variations
2 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-028-02 | Canopy gutter replacement Existing gutter found unserviceable on strip. | QR-VO-0872 | 19 Mar 2025 | $17,710 | Approved 1 Apr 2025, Melissa Trang |
| VAR-028-01 | Additional possession, Anzac weekend QR granted an extra possession that QClad resourced at short notice. | QR-VO-0881 | 10 Apr 2025 | $23,720 | Approved 22 Apr 2025, Melissa Trang |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.