This is what BHP Mitsubishi Alliance see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewClermont Coal: CHPP Conveyor Sheeting
Clermont, QLD · your contract BMA-CLM-CHPP-2023-6602
10 Oct 2023 to 24 Feb 2024 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$794,942
original $767,542 plus 1 approved variation
Work in place
$794,942
100% of the contract
Certified to date
$75,519
1 claim certified
Retention held
$0
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$117,754 of $117,754
$144,744 of $144,744
$245,760 of $245,760
$76,960 of $76,960
$48,024 of $48,024
$161,700 of $161,700
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2024-0074 | 2024-04 | 17 Mar 2024 | $75,519 | $75,519 | 5 Apr 2024 | 19 Apr 2024 | Paid |
Variations
1 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-021-01 | Conveyor cover extension, 40 lm Dust suppression audit extended the covered length. | BMA-VO-1802 | 12 Dec 2023 | $27,400 | Approved 26 Dec 2023, Warren Idle |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- No inspection plans on this job.