This is what ADCO Constructions see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewRNA Showgrounds: Pavilion Roof Renewal Stage 4
Bowen Hills, Brisbane, QLD · your contract ADC-RNA-S4-2023-4419
29 Aug 2023 to 27 Jan 2024 · QClad contact Cameron Hale, 0433 502 178
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$651,368
original $619,520 plus 1 approved variation
Work in place
$651,368
100% of the contract
Certified to date
$85,329
1 claim certified
Retention held
$0
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$209,764 of $209,764
$372,172 of $372,172
$31,848 of $31,848
$37,584 of $37,584
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2024-0058 | 2024-03 | 18 Feb 2024 | $85,329 | $85,329 | 8 Mar 2024 | 22 Mar 2024 | Paid |
Variations
1 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-018-01 | Heritage flashing detail to the pavilion parapet Heritage architect required a bespoke folded detail. | ADC-VO-1120 | 24 Oct 2023 | $31,848 | Approved 10 Nov 2023, Nadia Petkovic |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- No inspection plans on this job.