This is what MACH Energy, Mount Pleasant Operations see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewMount Pleasant Mine: Workshop Roofing
Mount Pleasant, Muswellbrook, NSW · your contract MACH-MP-WS-2023-8890
30 Jan 2024 to 22 Jun 2024 · QClad contact Cameron Hale, 0433 502 178
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$721,334
original $705,958 plus 1 approved variation
Work in place
$721,334
100% of the contract
Certified to date
$53,379
1 claim certified
Retention held
$0
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$118,222 of $118,222
$402,092 of $402,092
$54,720 of $54,720
$146,300 of $146,300
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2024-0140 | 2024-08 | 14 Jul 2024 | $53,379 | $53,379 | 2 Aug 2024 | 16 Aug 2024 | Paid |
Variations
1 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-014-01 | Additional safety mesh to the eastern bays Mine standard required mesh where the tender allowed harness only. | MACH-VO-0210 | 13 Mar 2024 | $15,376 | Approved 27 Mar 2024, Terry Bligh |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- No inspection plans on this job.