This is what Rio Tinto Aluminium see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewRio Tinto Boyne Smelters: Potline Cladding
Boyne Island, Gladstone, QLD · your contract RTA-BSL-PL-2022-3318
7 Feb 2023 to 1 Apr 2023 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$430,590
original $430,590 plus 0 approved variations
Work in place
$430,590
100% of the contract
Certified to date
$52,532
1 claim certified
Retention held
$0
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$78,286 of $78,286
$223,480 of $223,480
$94,720 of $94,720
$34,104 of $34,104
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2024-0031 | 2024-05 | 21 Apr 2024 | $52,532 | $52,532 | 10 May 2024 | 24 May 2024 | Paid |
Variations
0 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| No variations raised. | |||||
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- No inspection plans on this job.