QClad
QClad
PC-2026-0189 Demo M&A Apartments Stage 3: Facade Cladding · Jul 2026
Accounting connected Wed 5 Aug 2026
PC-2026-0189 Submitted Claim 3 · Jul 2026 PRJ-2026-045

Payment claim 3

M&A Apartments Stage 3: Facade Cladding · M&A Developments

Served

31 Jul 2026

Payment schedule due

21 Aug 2026

15 business days

Certified

-

Payment due

4 Sep 2026

25 business days

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0189

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

M&A Developments

ABN 35 604 118 262

Jordan Ellul, Development Manager

jordan@madevelopments.com.au

Maroochydore QLD

Contract

MAA-S3-CL-2026-0088

M&A Apartments Stage 3: Facade Cladding

Maroochydore, QLD

Reference date: 31 Jul 2026

Period: Jul 2026

Claim number: 3

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 item $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 item $2,680.00
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 45.76 day $57,108.48
RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle $94.50/m² 1,213.6 m² $114,685.20
RS-CLD-FIN Fielders Finesse architectural cladding, install $229.00/m² 542.8 m² $124,301.20
RS-CLD-KKP Fielders KingKlip 700 wall cladding, install $139.20/m² 357.2 m² $49,722.24
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 360.8 lm $41,131.20
RS-CLD-CAP Corner & parapet capping, supply and install $138.00/lm 161 lm $22,218.00
RS-WPF-MEM Liquid-applied weatherproof membrane $162.00/m² 128 m² $20,736.00
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 621.6 lm $21,631.68
RS-HGT-SPI Spider lift hire & operator, 28m $2,360.00/day 28.98 day $68,392.80
RS-CLD-FIN Fielders Finesse architectural cladding, install · VAR-045-01 Finesse set-out change to the northern elevation $229.00/m² 82.56 m² $18,906.24
RS-CLD-CAP Corner & parapet capping, supply and install · VAR-045-01 Finesse set-out change to the northern elevation $138.00/lm 32.68 lm $4,509.84
Value of work in place to date$536,813.71
Less previously claimed (claims 1-2)($330,216.63)
Value of work this claim, ex GST$206,597.08
Less retention at 5%($10,329.85)
Net, ex GST$196,267.23
GST at 10%$19,626.72
Amount claimed, inc GST$215,893.95

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 4 Sep 2026. Retention of $10,329.85 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0189

Claim history on PRJ-2026-045

Cumulative to date: $536,813.71 of a $1,090,514 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0178 Jun 2026 $219,579.95 30 Jun 2026 15 Jul 2026 31 Jul 2026 Paid
PC-2026-0171 May 2026 $110,636.68 29 May 2026 16 Jun 2026 1 Jul 2026 Paid