Payment claim 1
M&A Apartments Stage 3: Facade Cladding · M&A Developments
Served
29 May 2026
Payment schedule due
19 Jun 2026
15 business days
Certified
16 Jun 2026
Payment due
3 Jul 2026
Paid 1 Jul 2026
QClad
Roofing · Cladding · Acoustics
Payment claim
PC-2026-0171
Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)
Claimant
QClad Services Pty Ltd
ABN 62 138 704 915
QBCC 1174 320
Unit 2/9-11 Lenco Cres, Landsborough QLD 4550
07 5474 4966 · admin@qclad.com
Respondent
M&A Developments
ABN 35 604 118 262
Jordan Ellul, Development Manager
jordan@madevelopments.com.au
Maroochydore QLD
Contract
MAA-S3-CL-2026-0088
M&A Apartments Stage 3: Facade Cladding
Maroochydore, QLD
Reference date: 29 May 2026
Period: May 2026
Claim number: 1
Construction work carried out
| Item | Rate | Measured | Value, ex GST |
|---|---|---|---|
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 1 item | $18,450.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | $2,680.00/item | 1 item | $2,680.00 |
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 45.76 day | $57,108.48 |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | $94.50/m² | 1,213.6 m² | $114,685.20 |
| RS-CLD-FIN Fielders Finesse architectural cladding, install | $229.00/m² | 542.8 m² | $124,301.20 |
| RS-CLD-KKP Fielders KingKlip 700 wall cladding, install | $139.20/m² | 357.2 m² | $49,722.24 |
| RS-CLD-FLA Custom flashings, supply and install | $114.00/lm | 360.8 lm | $41,131.20 |
| RS-CLD-CAP Corner & parapet capping, supply and install | $138.00/lm | 161 lm | $22,218.00 |
| RS-WPF-MEM Liquid-applied weatherproof membrane | $162.00/m² | 128 m² | $20,736.00 |
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 621.6 lm | $21,631.68 |
| RS-HGT-SPI Spider lift hire & operator, 28m | $2,360.00/day | 28.98 day | $68,392.80 |
| RS-CLD-FIN Fielders Finesse architectural cladding, install · VAR-045-01 Finesse set-out change to the northern elevation | $229.00/m² | 82.56 m² | $18,906.24 |
| RS-CLD-CAP Corner & parapet capping, supply and install · VAR-045-01 Finesse set-out change to the northern elevation | $138.00/lm | 32.68 lm | $4,509.84 |
| Value of work in place to date | $110,636.68 |
| Less previously claimed (claims 1-0) | ($0.00) |
| Value of work this claim, ex GST | $110,636.68 |
| Less retention at 5% | ($5,531.83) |
| Net, ex GST | $105,104.85 |
| GST at 10% | $10,510.49 |
| Amount claimed, inc GST | $115,615.34 |
This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 3 Jul 2026. Retention of $5,531.83 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.
Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915
Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0171