PC-2026-0186 Demo BMA Saraji Workshop Upgrade: Cladding · Jul 2026
Accounting connected Wed 5 Aug 2026
PC-2026-0186 Submitted Claim 5 · Jul 2026 PRJ-2026-044

Payment claim 5

BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance

Lodged 31 Jul. BMA have until 21 Aug to issue the payment schedule under the BIF Act.

Served

31 Jul 2026

Payment schedule due

21 Aug 2026

15 business days

Certified

-

Payment due

4 Sep 2026

25 business days

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0186

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

BHP Mitsubishi Alliance

ABN 33 096 412 752

Warren Idle, Contracts Lead, Saraji

warren.idle@bhp.com

Dysart QLD

Contract

BMA-SAR-2026-1187

BMA Saraji Workshop Upgrade: Cladding

Saraji Mine, Dysart, QLD

Reference date: 31 Jul 2026

Period: Jul 2026

Claim number: 5

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 item $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 item $2,680.00
RS-PRE-IND Site induction & verification of competency $585.00/ea 16 ea $9,360.00
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 85.68 day $106,928.64
RS-LAB-TRV Travel & living away: per person, per day $385.00/day 428.8 day $165,088.00
RS-CLD-STR Strip existing wall cladding & dispose $48.60/m² 2,798.4 m² $136,002.24
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 2,138.4 m² $112,052.16
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install $136.80/m² 1,900.8 m² $260,029.44
RS-ROF-INS Roof insulation blanket 75mm R1.8, install $39.60/m² 1,900.8 m² $75,271.68
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 1,953.6 m² $48,449.28
RS-CLD-KL7 KLIP-LOK 700 wall cladding, install $142.40/m² 2,194.2 m² $312,454.08
RS-CLD-PUR Purlin & girt, supply and install $7,620.00/t 15.27 t $116,357.40
RS-CLD-LOU Weatherproof louvre panel, install $346.00/m² 70.56 m² $24,413.76
RS-CLD-DOR Personnel access door in cladding, form and trim $1,840.00/ea 3 ea $5,520.00
RS-ROF-VNT Ridge ventilator, supply and install $624.00/lm 33.6 lm $20,966.40
RS-ROF-RDG Ridge capping & barge, supply and install $146.00/lm 163.48 lm $23,868.08
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 793.6 lm $90,470.40
RS-HGT-SPI Spider lift hire & operator, 28m $2,360.00/day 58.8 day $138,768.00
RS-HGT-ANC Roof anchor point: supply, install & certify $745.00/ea 30.02 ea $22,364.90
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 1,308 lm $45,518.40
RS-CLD-PUR Purlin & girt, supply and install · VAR-044-01 Corroded purlin replacement, bays 4 to 9 $7,620.00/t 4.13 t $31,470.60
RS-CLD-LOU Weatherproof louvre panel, install · VAR-044-02 Additional louvre panels to the wash bay $346.00/m² 36.12 m² $12,497.52
RS-CLD-FLA Custom flashings, supply and install · VAR-044-02 Additional louvre panels to the wash bay $114.00/lm 73.96 lm $8,431.44
RS-CLD-DOR Personnel access door in cladding, form and trim · VAR-044-04 Second personnel door, eastern elevation $1,840.00/ea 0.12 ea $220.80
Value of work in place to date$1,700,039.19
Less previously claimed (claims 1-4)($1,326,423.85)
Value of work this claim, ex GST$373,615.34
Less retention at 5%($18,680.77)
Net, ex GST$354,934.57
GST at 10%$35,493.46
Amount claimed, inc GST$390,428.03

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 4 Sep 2026. Retention of $18,680.77 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0186

Claim history on PRJ-2026-044

Cumulative to date: $1,700,039.19 of a $2,533,376 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0179 Jun 2026 $393,279.31 30 Jun 2026 20 Jul 2026 - Certified
PC-2026-0173 May 2026 $393,279.31 29 May 2026 18 Jun 2026 28 Jul 2026 Paid
PC-2026-0166 Apr 2026 $328,924.51 30 Apr 2026 20 May 2026 26 Jun 2026 Paid
PC-2026-0158 Mar 2026 $210,940.72 31 Mar 2026 20 Apr 2026 29 May 2026 Paid