QClad
QClad
PC-2026-0179 Demo BMA Saraji Workshop Upgrade: Cladding · Jun 2026
Accounting connected Wed 5 Aug 2026
PC-2026-0179 Certified Claim 4 · Jun 2026 PRJ-2026-044

Payment claim 4

BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance

Served

30 Jun 2026

Payment schedule due

21 Jul 2026

15 business days

Certified

20 Jul 2026

Payment due

4 Aug 2026

25 business days

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0179

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

BHP Mitsubishi Alliance

ABN 33 096 412 752

Warren Idle, Contracts Lead, Saraji

warren.idle@bhp.com

Dysart QLD

Contract

BMA-SAR-2026-1187

BMA Saraji Workshop Upgrade: Cladding

Saraji Mine, Dysart, QLD

Reference date: 30 Jun 2026

Period: Jun 2026

Claim number: 4

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 item $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 item $2,680.00
RS-PRE-IND Site induction & verification of competency $585.00/ea 16 ea $9,360.00
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 85.68 day $106,928.64
RS-LAB-TRV Travel & living away: per person, per day $385.00/day 428.8 day $165,088.00
RS-CLD-STR Strip existing wall cladding & dispose $48.60/m² 2,798.4 m² $136,002.24
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 2,138.4 m² $112,052.16
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install $136.80/m² 1,900.8 m² $260,029.44
RS-ROF-INS Roof insulation blanket 75mm R1.8, install $39.60/m² 1,900.8 m² $75,271.68
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 1,953.6 m² $48,449.28
RS-CLD-KL7 KLIP-LOK 700 wall cladding, install $142.40/m² 2,194.2 m² $312,454.08
RS-CLD-PUR Purlin & girt, supply and install $7,620.00/t 15.27 t $116,357.40
RS-CLD-LOU Weatherproof louvre panel, install $346.00/m² 70.56 m² $24,413.76
RS-CLD-DOR Personnel access door in cladding, form and trim $1,840.00/ea 3 ea $5,520.00
RS-ROF-VNT Ridge ventilator, supply and install $624.00/lm 33.6 lm $20,966.40
RS-ROF-RDG Ridge capping & barge, supply and install $146.00/lm 163.48 lm $23,868.08
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 793.6 lm $90,470.40
RS-HGT-SPI Spider lift hire & operator, 28m $2,360.00/day 58.8 day $138,768.00
RS-HGT-ANC Roof anchor point: supply, install & certify $745.00/ea 30.02 ea $22,364.90
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 1,308 lm $45,518.40
RS-CLD-PUR Purlin & girt, supply and install · VAR-044-01 Corroded purlin replacement, bays 4 to 9 $7,620.00/t 4.13 t $31,470.60
RS-CLD-LOU Weatherproof louvre panel, install · VAR-044-02 Additional louvre panels to the wash bay $346.00/m² 36.12 m² $12,497.52
RS-CLD-FLA Custom flashings, supply and install · VAR-044-02 Additional louvre panels to the wash bay $114.00/lm 73.96 lm $8,431.44
RS-CLD-DOR Personnel access door in cladding, form and trim · VAR-044-04 Second personnel door, eastern elevation $1,840.00/ea 0.12 ea $220.80
Value of work in place to date$1,326,423.85
Less previously claimed (claims 1-3)($933,144.54)
Value of work this claim, ex GST$393,279.31
Less retention at 5%($19,663.97)
Net, ex GST$373,615.34
GST at 10%$37,361.53
Amount claimed, inc GST$410,976.87

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 4 Aug 2026. Retention of $19,663.97 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0179

Claim history on PRJ-2026-044

Cumulative to date: $1,326,423.85 of a $2,533,376 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0173 May 2026 $393,279.31 29 May 2026 18 Jun 2026 28 Jul 2026 Paid
PC-2026-0166 Apr 2026 $328,924.51 30 Apr 2026 20 May 2026 26 Jun 2026 Paid
PC-2026-0158 Mar 2026 $210,940.72 31 Mar 2026 20 Apr 2026 29 May 2026 Paid