Purlin and girt, Ceres shed 2
Bowen Steel Fixers · Purlin & girt installation
Raised by Marcus Deng on 13 Aug 2026 · on site 3 Sep 2026 to 17 Nov 2026
Waiting on a signature. Bowen Steel Fixers are already on the Bengalla job and their paperwork is current.
Ordered against claimed
What has been committed to them, what they have put in, and what is left to run. One row, not three pages.
Ordered
$344,920
the scope on this order
Claimed to date
$0
0 claims
Approved
$0
passed for payment
Retention held
$0
5% of approved
Left to run
$344,920
0% claimed
Scope
Purlin and girt installation to shed 2 ahead of the sheeting crews, to the joint venture's issued-for-construction drawings.
| Description | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Purlin and girt installation | 3,260 | lm | $104.00 | $339,040.00 |
| Site induction, Ceres | 7 | ea | $840.00 | $5,880.00 |
| Total, ex GST | $344,920.00 | |||
Their claims against this order
Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.
| Claim | Period | Received | Ex GST | Cumulative | Approved by | Status |
|---|---|---|---|---|---|---|
| Nothing claimed yetTheir first claim against this order will show here. | ||||||