QClad
QClad
WO-2026-0129 Demo Insulated panel, Hastings Deering workshop
Accounting connected Thu 13 Aug 2026
WO-2026-0129 Closed Work order QJ1939 CC-03 Wall cladding

Insulated panel, Hastings Deering workshop

Precision Thermal Insulation · Insulated panel & thermal

Raised by Cameron Hale on 17 Feb 2026 · on site 10 Mar 2026 to 27 Jun 2026 · approved by Cameron Hale on 18 Feb 2026

Complete and closed out. Retention released at practical completion.

Ordered against claimed

What has been committed to them, what they have put in, and what is left to run. One row, not three pages.

Ordered

$158,120

the scope on this order

Claimed to date

$28,750

1 claim

Approved

$28,750

passed for payment

Retention held

$1,438

5% of approved

Left to run

$129,370

18% claimed

Scope

Install insulated wall panel to the workshop annexe, including all trims and door surrounds.

DescriptionQtyUnitRateAmount
Insulated panel install 1,180 m² $134.00 $158,120.00
Total, ex GST$158,120.00

Their claims against this order

Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.

ClaimPeriodReceivedEx GSTCumulativeApproved byStatus
SCC-2026-0204 2026-06 8 Jul 2026 $28,750.00 $28,750.00 Cameron Hale Paid