WO-2026-0128 Demo Trade assistants, Hillgrove shutdown
Accounting connected Thu 13 Aug 2026
WO-2026-0128 In progress Work order QJ2047 CC-08 Direct labour & plant

Trade assistants, Hillgrove shutdown

Coral Coast Labour Hire · Labour hire, trade assistants

Raised by Cameron Hale on 7 Jul 2026 · on site 28 Jul 2026 to 12 Sep 2026 · approved by Cameron Hale on 8 Jul 2026

Suspended. Coral Coast's WorkCover certificate lapsed 1 Aug 2026 and nobody from this crew is on site until it is reinstated.

Coral Coast Labour Hire are suspended

Their WorkCover certificate lapsed on 1 Sep 2026. Nothing is approved or claimed against this order until it is reinstated on the subcontractor register.

Ordered against claimed

What has been committed to them, what they have put in, and what is left to run. One row, not three pages.

Ordered

$65,280

the scope on this order

Claimed to date

$36,720

1 claim

Approved

$0

passed for payment

Retention held

$0

0% of approved

Left to run

$28,560

56% claimed

$36,720 of that is in query and has not been passed for payment.

Scope

Trade assistants to QClad's own crew for the shutdown window. Day labour, supervised by QClad's leading hand.

DescriptionQtyUnitRateAmount
Trade assistant, day rate 96 day $680.00 $65,280.00
Total, ex GST$65,280.00

Their claims against this order

Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.

ClaimPeriodReceivedEx GSTCumulativeApproved byStatus
SCC-2026-0203 2026-07 6 Aug 2026 $36,720.00 $36,720.00 - Query Coral Coast are suspended, WorkCover certificate lapsed 1 Aug 2026. Nothing is paid until it is reinstated.