Scaffold to the workshop re-roof
Sunshine Coast Scaffolding · Scaffold erect & dismantle
Raised by Cameron Hale on 9 Jun 2026 · on site 7 Jul 2026 to 17 Oct 2026 · approved by Cameron Hale on 10 Jun 2026
Ordered against claimed
What has been committed to them, what they have put in, and what is left to run. One row, not three pages.
Ordered
$121,200
the scope on this order
Claimed to date
$55,440
1 claim
Approved
$55,440
passed for payment
Retention held
$2,772
5% of approved
Left to run
$65,760
46% claimed
Scope
Perimeter and internal birdcage scaffold to the workshop, erected in two stages to suit the staged roof strip.
| Description | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Scaffold erect and dismantle, staged | 2 | item | $38,400.00 | $76,800.00 |
| Weekly hire and inspection | 15 | week | $2,960.00 | $44,400.00 |
| Total, ex GST | $121,200.00 | |||
Their claims against this order
Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.
| Claim | Period | Received | Ex GST | Cumulative | Approved by | Status |
|---|---|---|---|---|---|---|
| SCC-2026-0205 | 2026-07 | 8 Aug 2026 | $55,440.00 | $55,440.00 | Cameron Hale | Approved |