WO-2026-0123 Demo Acoustic panel installation, Boyne potline
Accounting connected Thu 13 Aug 2026
WO-2026-0123 In progress Work order QJ2038 CC-04 Acoustics

Acoustic panel installation, Boyne potline

Noise Control Applicators · Acoustic panel installation

Raised by Marcus Deng on 5 May 2026 · on site 2 Jun 2026 to 24 Oct 2026 · approved by Adam Doyle on 7 May 2026

Ordered against claimed

What has been committed to them, what they have put in, and what is left to run. One row, not three pages.

Ordered

$485,840

the scope on this order

Claimed to date

$98,100

1 claim

Approved

$98,100

passed for payment

Retention held

$4,905

5% of approved

Left to run

$387,740

20% claimed

Scope

Install absorptive lining and barrier to the potline enclosure, to the acoustic report, including the post-installation verification test.

DescriptionQtyUnitRateAmount
Absorptive lining install 3,180 m² $114.00 $362,520.00
Mass-loaded barrier install 1,240 m² $96.00 $119,040.00
Verification sound test 1 item $4,280.00 $4,280.00
Total, ex GST$485,840.00

Their claims against this order

Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.

ClaimPeriodReceivedEx GSTCumulativeApproved byStatus
SCC-2026-0207 2026-07 8 Aug 2026 $98,100.00 $98,100.00 Marcus Deng Approved