Wall cladding, CHPP north and east elevations
Hunter Valley Cladding · Cladding, NSW crews
Raised by Cameron Hale on 26 May 2026 · on site 23 Jun 2026 to 26 Dec 2026 · approved by Adam Doyle on 28 May 2026
Ordered against claimed
What has been committed to them, what they have put in, and what is left to run. One row, not three pages.
Ordered
$556,080
the scope on this order
Claimed to date
$143,200
1 claim
Approved
$143,200
passed for payment
Retention held
$7,160
5% of approved
Left to run
$412,880
26% claimed
Scope
Install QClad-supplied wall cladding, insulated panel to the wash-down bay, and all associated trims.
| Description | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Wall cladding install | 6,420 | m² | $76.00 | $487,920.00 |
| Insulated panel to wash bay | 480 | m² | $142.00 | $68,160.00 |
| Total, ex GST | $556,080.00 | |||
Their claims against this order
Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.
| Claim | Period | Received | Ex GST | Cumulative | Approved by | Status |
|---|---|---|---|---|---|---|
| SCC-2026-0208 | 2026-07 | 5 Aug 2026 | $143,200.00 | $143,200.00 | Cameron Hale | Paid |