WO-2026-0121 Demo Purlin and girt replacement, Bengalla CHPP
Accounting connected Thu 13 Aug 2026
WO-2026-0121 In progress Work order QJ2044 CC-03 Wall cladding

Purlin and girt replacement, Bengalla CHPP

Bowen Steel Fixers · Purlin & girt installation

Raised by Cameron Hale on 26 May 2026 · on site 9 Jun 2026 to 5 Dec 2026 · approved by Adam Doyle on 28 May 2026

Ordered against claimed

What has been committed to them, what they have put in, and what is left to run. One row, not three pages.

Ordered

$283,080

the scope on this order

Claimed to date

$68,600

1 claim

Approved

$68,600

passed for payment

Retention held

$3,430

5% of approved

Left to run

$214,480

24% claimed

Scope

Remove and replace corroded purlins and girts to the CHPP walls, to the marked-up drawings, working around plant shutdown windows.

DescriptionQtyUnitRateAmount
Purlin and girt replacement 2,840 lm $98.00 $278,320.00
Coal site induction and site-specific training 7 ea $680.00 $4,760.00
Total, ex GST$283,080.00

Their claims against this order

Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.

ClaimPeriodReceivedEx GSTCumulativeApproved byStatus
SCC-2026-0209 2026-07 8 Aug 2026 $68,600.00 $68,600.00 Cameron Hale Approved