Rope access to the platform undersides
Highgate Access Solutions · Rope access & height safety
Raised by Marcus Deng on 19 Apr 2026 · on site 12 May 2026 to 8 Oct 2026 · approved by Marcus Deng on 20 Apr 2026
Highgate's WorkCover certificate lapses 14 Sep 2026. Nothing is claimed past that date until it is renewed.
Ordered against claimed
What has been committed to them, what they have put in, and what is left to run. One row, not three pages.
Ordered
$189,720
the scope on this order
Claimed to date
$30,600
1 claim
Approved
$0
passed for payment
Retention held
$0
5% of approved
Left to run
$159,120
16% claimed
$30,600 of that is in query and has not been passed for payment.
Scope
IRATA rope access for the sections no scaffold can reach, including all rigging, exclusion zones and rescue plan.
| Description | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| IRATA technician, two-person team | 62 | day | $3,060.00 | $189,720.00 |
| Total, ex GST | $189,720.00 | |||
Their claims against this order
Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.
| Claim | Period | Received | Ex GST | Cumulative | Approved by | Status |
|---|---|---|---|---|---|---|
| SCC-2026-0210 | 2026-07 | 7 Aug 2026 | $30,600.00 | $30,600.00 | - | Query Claiming 5 days where the docket book shows 4. Held pending the site diary. |