WO-2026-0119 Demo Scaffold erect, hire and dismantle, four stations
Accounting connected Thu 13 Aug 2026
WO-2026-0119 In progress Work order QJ2041 CC-01 Preliminaries & establishment

Scaffold erect, hire and dismantle, four stations

Sunshine Coast Scaffolding · Scaffold erect & dismantle

Raised by Marcus Deng on 10 Mar 2026 · on site 17 Mar 2026 to 21 Nov 2026 · approved by Nathan Carter on 12 Mar 2026

Ordered against claimed

What has been committed to them, what they have put in, and what is left to run. One row, not three pages.

Ordered

$331,360

the scope on this order

Claimed to date

$86,400

1 claim

Approved

$86,400

passed for payment

Retention held

$4,320

5% of approved

Left to run

$244,960

26% claimed

Scope

Design, erect, maintain, inspect weekly and dismantle access scaffold to all four station canopies. Handover certificates on each erection.

DescriptionQtyUnitRateAmount
Scaffold erect and dismantle, per station 4 item $48,600.00 $194,400.00
Weekly hire and inspection 32 week $4,280.00 $136,960.00
Total, ex GST$331,360.00

Their claims against this order

Monthly, measured against the scope above. A claim in query is still counted as claimed, because it is still money they believe they are owed.

ClaimPeriodReceivedEx GSTCumulativeApproved byStatus
SCC-2026-0212 2026-07 8 Aug 2026 $86,400.00 $86,400.00 Marcus Deng Approved