This is what M&A Developments see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewM&A Apartments Stage 3: Facade Cladding
Maroochydore, QLD · your contract MAA-S3-CL-2026-0088
26 May 2026 to 7 Nov 2026 · QClad contact Cameron Hale, 0433 502 178
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$1,090,514
original $1,063,286 plus 1 approved variation
Work in place
$564,473
52% of the contract
Certified to date
$330,217
2 claims certified
Retention held
$16,511
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$192,924 of $293,354
$260,789 of $585,256
$68,393 of $108,560
$42,368 of $103,344
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0189 | 2026-07 | 8 Aug 2026 | $206,597 | - | 28 Aug 2026 | 11 Sep 2026 | Submitted |
| PC-2026-0178 | 2026-06 | 8 Jul 2026 | $219,580 | $219,580 | 29 Jul 2026 | 12 Aug 2026 | Paid |
| PC-2026-0171 | 2026-05 | 6 Jun 2026 | $110,637 | $110,637 | 26 Jun 2026 | 10 Jul 2026 | Paid |
PC-2026-0189, lodged 8 Aug 2026. A payment schedule has not been received. Under s.76 of the Act, a respondent who does not issue one inside the statutory period becomes liable for the full claimed amount.
Variations
1 approved and in the contract sum above. 1 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-045-02 | Spider lift extended hire, 3 weeks Programme slip on the preceding trade left the lift on site three weeks longer. | MAA-VO-0038 | 31 Jul 2026 | $35,400 | Submitted |
| VAR-045-01 | Finesse set-out change to the northern elevation Architect revised the panel module after the shop drawings were approved; sheets recut. | MAA-VO-0031 | 25 Jun 2026 | $27,228 | Approved 9 Jul 2026, Jordan Ellul |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- Facade cladding, M&A Stage 3 ITP-045-01 2 of 4 signed