QJ2045 On site

M&A Apartments Stage 3: Facade Cladding

Maroochydore, QLD · your contract MAA-S3-CL-2026-0088

26 May 2026 to 7 Nov 2026 · QClad contact Cameron Hale, 0433 502 178

Your subcontractor

QClad Services Pty Ltd

ABN 62 138 704 915 · QBCC 1174 320

Contract sum

$1,090,514

original $1,063,286 plus 1 approved variation

Work in place

$564,473

52% of the contract

Certified to date

$330,217

2 claims certified

Retention held

$16,511

5%, half released at PC

Progress by area

Measured on site, not estimated. This is the same measure the claim is built from.

Preliminaries & establishment 66%

$192,924 of $293,354

Wall cladding 45%

$260,789 of $585,256

Height access & safety systems 63%

$68,393 of $108,560

Weatherproofing 41%

$42,368 of $103,344

Progress claims

Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.

1 awaiting your payment schedule
ClaimPeriodLodgedClaimed, ex GSTCertifiedSchedule duePayment dueStatus
PC-2026-0189 2026-07 8 Aug 2026 $206,597 - 28 Aug 2026 11 Sep 2026 Submitted
PC-2026-0178 2026-06 8 Jul 2026 $219,580 $219,580 29 Jul 2026 12 Aug 2026 Paid
PC-2026-0171 2026-05 6 Jun 2026 $110,637 $110,637 26 Jun 2026 10 Jul 2026 Paid

PC-2026-0189, lodged 8 Aug 2026. A payment schedule has not been received. Under s.76 of the Act, a respondent who does not issue one inside the statutory period becomes liable for the full claimed amount.

Variations

1 approved and in the contract sum above. 1 submitted and awaiting your determination.

VariationWhat and whyYour referenceRaisedValue, ex GSTStatus
VAR-045-02 Spider lift extended hire, 3 weeks Programme slip on the preceding trade left the lift on site three weeks longer. MAA-VO-0038 31 Jul 2026 $35,400 Submitted
VAR-045-01 Finesse set-out change to the northern elevation Architect revised the panel module after the shop drawings were approved; sheets recut. MAA-VO-0031 25 Jun 2026 $27,228 Approved 9 Jul 2026, Jordan Ellul

Documents issued to you

Current revision only. A superseded revision is never issued twice.

  • Nothing issued yet.

Inspection and test plans

Hold points and witness points on your job, with what has been signed.

  • Facade cladding, M&A Stage 3 ITP-045-01 2 of 4 signed

QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320 · 07 5474 4966 · admin@qclad.com. Figures on this page are drawn live from QClad's records at 13 Aug 2026 and are the same figures the claim is built from. Queries to Cameron Hale, cameron@qclad.com.