This is what BHP Mitsubishi Alliance see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewBMA Saraji Workshop Upgrade: Cladding
Saraji Mine, Dysart, QLD · your contract BMA-SAR-2026-1187
24 Mar 2026 to 3 Oct 2026 · QClad contact Cameron Hale, 0433 502 178
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$2,533,376
original $2,470,624 plus 3 approved variations
Work in place
$1,787,633
71% of the contract
Certified to date
$1,326,424
4 claims certified
Retention held
$66,321
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$137,419 of $195,158
$540,637 of $768,536
$737,838 of $1,020,868
$161,133 of $226,550
$45,518 of $75,864
$165,088 of $246,400
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0186 | 2026-07 | 8 Aug 2026 | $373,615 | - | 28 Aug 2026 | 11 Sep 2026 | Submitted |
| PC-2026-0179 | 2026-06 | 8 Jul 2026 | $393,279 | $393,279 | 29 Jul 2026 | 12 Aug 2026 | Certified |
| PC-2026-0173 | 2026-05 | 6 Jun 2026 | $393,279 | $393,279 | 26 Jun 2026 | 10 Jul 2026 | Paid |
| PC-2026-0166 | 2026-04 | 8 May 2026 | $328,925 | $328,925 | 29 May 2026 | 12 Jun 2026 | Paid |
| PC-2026-0158 | 2026-03 | 8 Apr 2026 | $210,941 | $210,941 | 29 Apr 2026 | 13 May 2026 | Paid |
PC-2026-0186, lodged 8 Aug 2026. A payment schedule has not been received. Under s.76 of the Act, a respondent who does not issue one inside the statutory period becomes liable for the full claimed amount.
Variations
3 approved and in the contract sum above. 1 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-044-05 | Rejected (additional travel for the June roster change Roster changed from 2:1 to 3:1 for two swings, adding travel and LAFHA. | BMA-VO-2284 | 10 Jul 2026 | $18,480 | Rejected |
| VAR-044-04 | Second personnel door, eastern elevation Site requested an additional access door after the layout changed. | BMA-VO-2291 | 24 Jul 2026 | $1,840 | Approved 5 Aug 2026, Warren Idle |
| VAR-044-03 | Crane isolation standby, 4 shifts lost Overhead crane could not be isolated on four programmed shifts; crew stood by on site. | BMA-VO-2276 | 2 Jul 2026 | $46,944 | Submitted |
| VAR-044-02 | Additional louvre panels to the wash bay BMA added ventilation to the wash bay after a hygiene assessment. | BMA-VO-2248 | 5 Jun 2026 | $24,336 | Approved 19 Jun 2026, Warren Idle |
| VAR-044-01 | Corroded purlin replacement, bays 4 to 9 Six bays of purlin found beyond repair once the cladding came off. Latent condition. | BMA-VO-2211 | 23 Apr 2026 | $36,576 | Approved 14 May 2026, Warren Idle |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- QJ2044 Crane isolation procedure DOC-4372 · Safety plan · updated 28 Jul 2026 Rev C
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- Workshop roof and wall cladding, Saraji ITP-044-01 3 of 5 signed