This is what Rio Tinto Aluminium see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewRTAY Yarwun Central Workshop: Cladding
Yarwun, Gladstone, QLD · your contract RTA-YAR-CW-2024-5518
15 Oct 2024 to 5 Apr 2025 · QClad contact Cameron Hale, 0433 502 178
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$897,150
original $897,150 plus 0 approved variations
Work in place
$897,150
100% of the contract
Certified to date
$104,069
1 claim certified
Retention held
$0
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$142,714 of $142,714
$115,404 of $115,404
$471,600 of $471,600
$110,360 of $110,360
$57,072 of $57,072
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2025-0061 | 2025-05 | 20 Apr 2025 | $104,069 | $104,069 | 9 May 2025 | 23 May 2025 | Paid |
Variations
0 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| No variations raised. | |||||
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- No inspection plans on this job.